Disassembly
16
CVHM-SVN001C-EN
b. Remove the suction elbow bolts at the compressor
and evaporator connections.
c. Lift the suction elbow from the chiller being careful
to avoid damage to flange surfaces.
Note:
Compressor assembly can be removed
with wrap pipe still installed.
d. Unbolt the economizer vent pipe at the first stage
volute connection and at the economizer
connection.
e. The two-piece wrap pipe has four lifting tabs. You
will need three lifting clevises to remove the pipe. A
Crosby screw pin shackle, model S-209, stock
number 1018482 with a 5/8-in. pin is acceptable as
shown in
.
f. Remove the first stage discharge volute bolts and
the second stage suction bolts.
7.
If required by installation dimension constraints,
remove the two-piece wrap pipe. The wrap pipe can be
disassembled at the mid-flange joint.
a. Lift the wrap pipe from the chiller, being careful to
avoid damaging flange surfaces.
b. Install protective covers on the evaporator, wrap
pipe, and compressor connections. Plastic secured
with duct tape makes an adequate cover if no heavy
objects are set on the openings.
c. Remove the second stage volute-to-condenser
bolts.
8. Use designated lift point for level lift.
a.
If the wrap pipe is still on the unit
, see
b.
If lifting the compressor only (no wrap pipe)
, see
.
9. Support compressor on wood blocks or plywood to
prevent damage to the compressor or wrap pipe
components.
Figure 10.
Lifting clevis on the suction elbow lifting tab
Figure 11.
Wrap pipe lifting points (requires three
5/8-in. shackles to lift)
Figure 12.
Compressor-only lifting points
Figure 13.
Casting identifies lifting points by
component
Lift points for
M20 swivel D-rings