CDHF-SVX01N-EN
95
Appendix A: Forms and Check Sheets
The following forms and check sheets are included for
use with Trane start-up of CDHF and CDHG
CenTraVac™ chillers. Forms and check sheets are used,
as appropriate, for installation completion verification
before Trane start-up is scheduled, and for reference
during the Trane start-up.
Where the form or check sheet also exists outside of
this publication as standalone literature, the literature
order number is also listed.
•
“Appendix B: CenTraVac™ Chiller Installation
Completion and Request for Trane Service,” p. 96
(CTV-ADF001*-EN)
•
“Appendix C: CDHF and CDHG CenTraVac™ Chiller
Start-up Tasks to be Performed by Trane,” p. 98
•
“Appendix D: CDHF and CDHG CenTraVac™ Chiller
Annual Inspection List,” p. 100
•
“Appendix E: CDHF and CDHG CenTraVac™ Chiller
Operator Log,” p. 101
Unit Start-up/Commissioning
IIm
mp
po
orrtta
an
ntt:: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane®
products. Contractor shall provide Trane
(or an agent of Trane specifically
authorized to perform start-up) with notice
of the scheduled start-up at least two weeks
prior to the scheduled start-up.