Test fuel pressure interlock switches. With burner in normal operation (preferably at high fire), raise
low gas pressure switch setpoint above available fuel pressure. Burner must shut off when visual
indicator trips. Test high gas pressure switch by reducing setpoint below existing manifold pressure.
Again, burner must shut off when indicator trips. After returning to normal setpoint, burner must not
restart until switches have been manually reset.
10.
Manually lift safety valve with test lever momentarily while boiler is at normal operating pressure.
You should see flow out of this valve. If the valve does note flow when opened, or properly close
afterwards, refer to the safety relieve valves manual for further details.
11.
Check the Flue gas connector, vent connector (breaching), and stack for leaking and or corrosion. All
vent system components and draft controls shall be check per their manuals or instructions provided
by the installer.
8.2.4 Semi-Annual procedure, also reference the burner manual’s procedures.
1.
Cool boiler slowly to room temperature. NOTE: Failure to cool boiler slowly can cause plates to leaks.
This is very important! To assist cool down, use the Test/Run or Check/Run switch located on the
programmer to run the blower.
2.
Remove all the nuts from the front door, pry the door loose from the boiler and swing it away on the
davit arm.
3.
Clean the combustion chamber.
4.
Clean the sight port glass, replace if required.
5.
Clean & Adjust pilot Assembly. This will be covered in the burner manual. **
6.
Re-calibrate all indicating and recording devices
7.
Check flame failure detection system components. Refer to the burner manual for additional
instructions.
8.
Check firing rate control. **
9.
Check piping and wiring of all interlocks and shut off valves. **
10.
Inspect burner components; refer to the burner manual for additional instructions. **
11.
Check wire insulation for brittleness, cracking, or missing patches.
12.
Disassemble and clean all safety control related piping – LWCO equalizers, pressure control manifolds,
and air flow switch tubes.
13.
Check boiler pressure gauge against calibrated master gauge or with dead weight tester. New gauges
are built to one percent (1%) accuracy.
8.2.5 Annual procedure, also reference the burner manual’s procedures.
1.
Follow steps 1 through 10 listed under Semi-Annual Procedure.
2.
Clean water side of boiler as follows:
Cool and drain the boiler.
Wash down the inside (water side) of the boiler with a hose, making sure to get all sludge and
scale out of bottom of boiler.
Содержание Triumph 1000
Страница 14: ...14 TRIAD Boiler Systems Inc West Chicago IL www triadboiler com Handling Options ...
Страница 16: ...16 TRIAD Boiler Systems Inc West Chicago IL www triadboiler com 2 0 Boiler Component Identification ...
Страница 20: ...20 TRIAD Boiler Systems Inc West Chicago IL www triadboiler com Model 300 500 Model 750 1000 ...
Страница 27: ...27 TRIAD Boiler Systems Inc West Chicago IL www triadboiler com 2 6 Example wiring diagrams ...