Important: preparation works
• Connect control panels, safety devices and motors under consideration of the safety regulations.
Attention: if no stop switch is connected then the terminals 31/37 have to be bridged ( Slave).
• Turn on the equipment (Master and Slave) (correct connection being preconditioned).
•
Important:
Putting into operation in Impulse mode (standard setting) and not in dead man mode.
• During initial operation the choice of language is the first adjustment (Slave + Master).
• After that the slave control carries out a system test. If an error occurs, a message appears in the display. With the
ENTER
button
you get into the
MAIN MENU
to perform parameter changes. Exit using
ESC button
- is the further system
test completed successfully „End positions being detected“ appears in the display - the slave control waits for a pulse of
the master control.
• After choice of the language the most important operating parameters can be set within the
BASIC SETTINGS
of the
master control. Exit using
ESC button
- system tests of the master control are carried out. If an error occurs you get into
the BASIC SETTINGS again by pressing the
ENTER button.
• After the successfull system test of the master also in its display „End positions being detected“ appears.
• Now if the master receives an impulse (transmitter, impulse button) the automatic detection of limit positions of the master´s
and the slave´s boom is started. After successful completion „Ready for use“ appears in both displays.
If for any reason one of the two control boards is being exchanged without the other, then first of all, the
command „delete positions“ in the menu „diagnosis“ has to be executed.
7. Putting into operation
Barrier control ST 80, ST 80V / Master-Slave
LANGUAGE SELECTION for slave control
•
Can be selected during initial operation (hence after reset to factory settings).
• Can be also chosen by pressing the
ESC button
( ) for 5s, from any position in menu.
Slave control
S
Putting into operation
$$$$$$$$$$$$$$$$
$$$$$$$$$$$$$$$$
language:
English
$$$$$$$$$$$$$$$$
$$$$$$$$$$$$$$$$
Tousek Digital
2
1
2
scroll
confirm
$$$$$$$$$$$$$$$$
$$$$$$$$$$$$$$$$
System test
Main safety edge
$$$$$$$$$$$$$$$$
$$$$$$$$$$$$$$$$
End positions
being detected
$$$$$$$$$$$$$$$$
$$$$$$$$$$$$$$$$
Open position
being detected
$$$$$$$$$$$$$$$$
$$$$$$$$$$$$$$$$
Close position
being detected
$$$$$$$$$$$$$$$$
$$$$$$$$$$$$$$$$
Ready for use
3
Slave barrier
Impulse
from
Master