V. Installation of “TMR140 Series”
1. Preparatory
Procedure
(1) Make sure the transportation plan for “TMR140 Series” including a carry-in route.
(2) Arrange all necessary equipments for unloading “TMR140 Series” from the truck,
such as a cargo crane, a wrecker, and a forklift.
(3) Prior to installation, please confirm that all necessary works in the membrane
submerged tank are completed. All waste from the tank, such as concrete clusters,
scrapes and mill ends, should be removed completely.
2. Unloading
Products
Unload "TMR140 Series” with a cargo crane, or a wrecker, or a forklift.
Please note the followings
for unloading "TMR140 Series".
(1) The element block and the aeration block are separately packed and delivered.
The element block contains a fixed number of membrane elements installed in it.
(2) When lifting "TMR140 Series" (or lifting the element block or the aeration block
separately), please set a hook on all hang holes and lift it keeping it horizontal.
Please be careful not to damage element nozzles, air diffusers or other components.
Please ensure safety anytime when doing these operations.
When lifting “TMR140 Series”, please attach chains or slings to it
and lift it straight upward
calmly
to prevent “TMR140 Series” from
shaking. Never allow any person under “TMR140 Series”.
Please use chains or slings compatible with lifting weight.
Be sure to set down the module where there is no obstacle.
Otherwise, the module may topple down and get damaged.
3. Checking
Products
Please check the followings soon after carrying in “TMR140 Series”:
(1)
All items are delivered as stated in the shipping ticket.
(2)
No damage is caused in transit.
(3)
The protective covers are fit in the right position.