8
1) After unloading the lift, place it near the intended
installation location.
2) Remove the shipping bands and protective wrapping
from the lift. Support the top column as you remove the
packing frames from each end of the lift. Be sure to set
the columns down onto a block of wood to avoid any
damage.
3)
Remove all loose components from the lift columns and
set aside. This is a good time to tighten the top plates
of the columns if needed and check the contents of the
parts box to ensure that you have all the components
needed to complete this install.
4) Once you determine where you want to install the lift, check to make sure there are no
obstructions in the ceiling that may interfere when standing the columns up. If clear, go
ahead and stand the columns up at his time.
5) Position the columns facing each other 134.75” from the outside
of the base plates; then install the locking system components into
each column (refer to pictures). Be sure to secure the ends of the lock
spindle with the provided C-Clips. Once installed, raise each carriage to
the first safety lock.
NOTE:
The power unit column is referred to as the
main side column and the non-power unit column is referred to as the
offside column.
6) Once one of the lift columns is positioned, using a 3/4” concrete drill
bit, drill the anchor bolt holes through the baseplate of the column,
installing anchors as you go. Thread the nut to the top of anchor and
carefully tap them into the holes drilled into the concrete.
7) Using a level, check column for side-to-side plumb and front-to-back
plumb. It is very important that the columns are perfectly plumb in
both directions. Failure to do this could result in premature wear on the
lifting components and/or pad movement while lifting a vehicle. Use
the provided shims to shim the lift column as needed by placing them
around the anchor. Once the column is perfectly plumb, torque 3/4”
anchor bolts to
85 ft-lbs
using a torque wrench
NOTE: DO NOT USE
IMPACT WRENCH.
6-INSTALLATION INSTRUCTIONS
PLEASE NOTE THAT ALL DIMENSIONS GIVEN ARE FOR REFERENCE. FINAL
DIMENSIONS MAY VARY SLIGHTLY. LIFT COLUMNS MUST BE PLUMB AND
SQUARE REGARDLESS OF FINAL DIMENSIONS.
MAIN SIDE
OFFSIDE
Содержание PREMIER HD2P-9KFP
Страница 25: ...21 11 DIAGRAMS FIG 1 9 FIG 1 HD2P 9KFP...
Страница 26: ...22 FIG 2 HD2P 9KFP Column Anchor Bolts 3 4 6 25 Column 4 Concrete 3000PSI min...
Страница 27: ...23 FIG 3 HD2P 9KFP...
Страница 33: ...29 FIG 9 CABLES HOSES...
Страница 38: ......
Страница 39: ...NOTES...