ACT6000 User Guide
– January 2021 Page 37 of 52
Multi-section Setup
If the line is realized by different cables type, (as the following example) using the detailed
plant map, it is suggested to perform this test following these instructions:
From the
Multimeter
menu select and enter
on the
“
4. RES. MULTI-SECTION SETUP
”.
Type the right diameter (Ø mm) (or AWG
type) and set the right length (L m) of
each section.
Then, exit from this menu and select the
Insulation test
as describer on previous page.
Finished the
Insulation test
, select and perform the
RFL test
as already described.
Finished the fault localization, under the diagram will be shown a color bar that highlights
the different cable sections.
>>>
Attention!
This multi-section setup will stay even after the switch-off of the instrument !
To avoid errors on other possible fault localizations, restore the default condition pushing
the
F1
key
“
Default
” from the
Config & Utility
menu.