21
LOADING/UNLOADING MACHINE FOR
TRANSPORTING
When transporting the machine by use of trailer or
truck, carefully follow the loading and tie-down
procedure:
1. Raise the scrub head and remove squeegee
assembly.
2. Use a ramp that can support the machine weight
and operator and carefully load machine. Do not
operate the machine on a ramp incline that
exceeds a 21% grade level (Figure 47). A winch
must be used when ramp incline exceeds a 21%
grade level.
FOR SAFETY: When loading/unloading machine
onto/off truck or trailer, use a ramp that can
support the machine weight and operator.
FOR SAFETY: Do not operate the machine on a
ramp incline that exceeds a 21% grade level.
FIG. 47
3. Once loaded, position the front of the machine up
against the front of the trailer or truck. Lower the
scrub head, turn key off and set parking brake, if
equipped (Figure 48).
4. Place a block behind each wheel (Figure 48).
5. Using tie-down straps, secure the machine using
the four tie-down brackets located on the machine
frame (Figure 48). It may be necessary to install
tie-down brackets to the floor of your trailer or
truck.
ATTENTION: Do not use control console area
or accessory storage rails for tie-down
locations, damage may occur.
FIG. 48
STORING MACHINE
The following steps should be taken when storing the
machine for extended periods of time.
1. Charge the batteries before storing machine to
prolong the life of the batteries. Recharge batteries
once a month.
2. Disconnect batteries before storing.
3. Drain and rinse recovery tank and solution tank.
4. Store the machine in a dry area with squeegee and
scrub head in the up position.
ATTENTION: Do not expose machine to rain, store
indoors
.
5. Open the recovery tank lid to promote air
circulation.
NOTE: To prevent potential machine damage store
machine in a rodent and insect free environment.
FREEZE PROTECTION
Storing machine in freezing temperatures.
1. Completely drain solution tank and recovery tank.
2. Empty the water from the solution tank filter located
under machine. Replace filter.
3. Pour 1 gallon / 4 liters of propylene glycol based
recreational vehicle (RV) antifreeze into the
solution tank.
4. Turn machine on and operate the solution flow
system. Turn the machine off when the antifreeze
is visible on floor.
5. After storing machine in freezing temperatures,
drain any remaining antifreeze from the solution
tank. Add clean water to solution tank and operate
the machine to flush system.