LTX Patch and Splice Panel
LTX Patch and Splice Panel
Fiber :: Install guide
•
LTX Patch and Splice Panel
•
Tray platform
•
Splice trays
•
Splice sleeve holders
•
Arcs (edge protectors)
•
Velcro bands
•
Routing spools
2.2.1 Contents
•
Removable doors (spring-hinged swing down)
•
Designation labels (front and rear)
•
Cable clamp bracket
•
Cable clamp with bushing sleeves
•
Mounting brackets (to mount to 19
"
or 23
"
rack)
•
Installation guide
2.3 Installation Guidelines
•
Elevated Operating Ambient Temperature
- If installed in a closed or multi-unit rack assembly, the operating ambient temperature
of the rack environment may be greater than room ambient. Therefore, consideration should be given to installing the equipment in an
environment compatible with the maximum ambient temperature (Tma) specified by the manufacturer.
•
Mechanical Loading
- Mounting of the equipment in the rack should be such that a hazardous condition is not achieved due to uneven
mechanical loading.
•
Reliable Earthing
- Reliable earthing of rack-mounted equipment should be maintained. Particular attention should be given to supply
connections other than direct connections to the branch circuit (e.g. use of power strips).
2.4 Location and Space
The LTX Patch and Splice Panel requires space in the front and rear for access to patching, splicing, and cabling. Leave as much side
clearance for tray and panel removal and worker access as required by your application or local regulations. Plan the input/output, upward/
downward (cable feed) layout of each panel and its position in the rack before beginning LTX panel installation.
LTX panels adapt to standard 19
"
or 23" ETSI racks with EIA, ETSI, and WECO spacing and nominal 3¼" extensions beyond the front rack
fl ange.
No special tools required.
2.5 Tools and Equipment