100A/60A Universal Voltage GMT Fuse Panels
With Enhanced Power/Fuse & Bay Alarms
Power
:: HPGMTXX & GMTXX
ALERT
!
ALERT! Only use components and crimping tools approved by agencies or certifying bodies recognized
in your country or region, such as Underwriter’s Laboratories (UL), TUV, etc.
5. Use a listed (approved) crimping tool to attach a
listed (approved), dual-hole, right-angle
compression lug for #10 studs on 5/8-in. centers
onto #6 AWG ground wire. (Min. #8 AWG for a
100A feed; #10 AWG for a 60A feed.)
6. If desired (highly recommended), lightly coat
anti-oxidant on lug, grounding terminal, and
surrounding contacting surface.
7. Connect the lug using the #10-32 KEPS nuts and
flatwashers provided, as shown in Figure 5.
8. Tighten KEPS nuts to ~20 in.-lb (~2.3 N•m), max.
9. Make sure input power is off (open breaker,
phoney fuse, or open fuse holder at primary power
distribution unit [PDU]) before connecting this
panel’s input cables to that PDU.
10. For input wiring — wiring used as inputs to this distribution the panel — do one of the following: (Refer to the
following illustrations.)
For input wiring on a 100A panel — (see page 9 for 60A input wiring instructions)
a. Crimp dual-hole compression lugs onto #8 to #1/0 AWG conductors (#1/0 AWG with a 60C insulation rating,
minimum for a 100A feed). Insulate lug barrels with UL94 V-0 rated heat-shrink tubing.
b. Clean terminals and lugs with an nonabrasive, nonmetallic cloth.
c. If desired (highly recommended), lightly coat anti-oxidant on lugs, terminals, and contacting surfaces.
d. Connect lugs to input
BATT
and
RTN
terminals on the panel.
e. Torque KEPS nuts to ~50 in.-lb (~5.6 N•m), max.
11. Make sure GMT fuse positions are either empty or contain dummy fuses (phoney, inoperative, all-plastic slugs).
Figure 5 - Ground Lug Connection
WARNING
!
WARNING! Before connecting input power cables, make sure the input power to the panel is turned off.