4. Search the route in passive mode

The source of the electromagnetic field in this case are frequency currents 50 Hz in cables under 

mains voltage and 100 Hz in pipelines with cathodic protection mode, the route search is performed 
without using the trace generator. Equipment used: Receiver «AP-014», Electromagnetic sensor 
«EMD-247», headphones.

5. Place the electromagnetic sensor «EMD-247» exactly on the track and so, that it will be at

the point of maximum signal strength. For this you need to have the sensor perpendicular to the 
desired track at that distance from it, where you want to search;

4.

Select the work «passive» frequency (50 Hz for tracing cable under voltage or

100 Hz for the tracing of the pipeline with cathodic protection.

6.Press the «Change receiver sensitivity» buttons to adjust the input level, so the level

filled led scale as much as possible, but to the last led isn’t flashing.

When switching on, the device revert to the settings used in previous work - the 

level of input gain, volume levels and frequency filtering.

If while working full scale led filled, and the last led is flashing (there is an overload of 

the input), the receiver sensitivity should be reduced.

If the maximum of the sensitivity scale isn’t filled, and the first led flashes, it means 

that the device cannot recognize the signal at the selected frequency, because its level 
is too low or signal is missing.

Preparing Receiver AP-014 for operation

1. Insert  two  batteries  into  the  battery  compartment  of  the

receiver «AP-014», observing polarity.

2. Connect  the  electromagnetic  sensor,  headphones  to  the

corresponding connectors of the receiver.

7. Establish a comfortable level of headphone volume with «Headphone volume Changes»

buttons.

8.

Move along the path by moving the electromagnet sensor across tracks in one or the other

way  to  determine  the  point  with  the  strongest  signal.  Points  with  the  utmost  level  of  the  signal 

correspond to the position of the communication axis.

3.Turn on the power of the receiver.

Содержание Success CBI-116N

Страница 1: ......

Страница 2: ...view and buttons mapping 5 2 2 Receiver control and indication modes 6 3 Electromagnetic sensor EMD 247 8 4 Search the route in passive mode 9 4 1 Route location methods 10 5 Additional features 11 5...

Страница 3: ...nst external influences IP 54 1 2 The principle of operation The principle of operation of the cable locator is based on phenomenon of electromagnetic induction The electromagnetic E D 247 sensor reco...

Страница 4: ...ed signal Visual indication Voltage 1 8 to 4V alkaline batteries type 1 5 V 2 pcs Time of continuous operation not less than 10 hours Operation temperature 300 500 Location precision m 0 3 Ingress pro...

Страница 5: ...the dimensions of the cell phone has a built in micro processor 2 1 General view and buttons mapping Sensor connector Headphone connector Led scale Sensitivity Volume On Off Pause Frequency and sound...

Страница 6: ...nto the operating mode the LED display is indicated by the input signal level at a selected frequency and a synthesized audio signal is given on headphones Turning off the receiver is performing by br...

Страница 7: ...indication Duringlongretentionofthebutton Frequency switch the device switches the mode of audio indication Three audio indication modes are implemented in the receiver The natural sound mode The soun...

Страница 8: ...tenna 50 Hz 100 Hz 512 Hz 1024 Hz 8192 Hz and 32768 kHz Switching of resonance is forced controlled by the receiver Lock nut rod Locking antenna nut Rod The EMD Rod for easy transportation is sliding...

Страница 9: ...switching on the device revert to the settings used in previous work the level of input gain volume levels and frequency filtering If while working full scale led filled and the last led is flashing t...

Страница 10: ...um method is intended for a quick route location Flat peaks of the signal level curve do not allow for high location accuracy but enables a quick route location 2 The Minimum method When the EMD senso...

Страница 11: ...of the utilities when the antenna axis intersects the axis of the route This is the indirect method of measuring the depth of utility fig 5 1 5 2 Task Detecting the pipeline and utility lines interse...