5
FITTING THE JUNCTION BOX LEAD ONTO THE
LOADER
A 6 metre twin core cable with 7.5 amp blade type fuse
is supplied with the machine. The end with two eyelets
must be fitted to the battery of the loader with the cable
routed in a suitable position without causing damage to
the lead during operation. If the connector provided on
the supply lead is not to be used, it is essential that the
7.5 amp fuse is retained to prevent damage resulting
from current overload.
If the control box loses connection to the bluetooth box
on the machine, it will need to be paired again. Unplug
the control box in the cab, wait ten seconds and
re
-
insert. If the connection is still unsuccessful, unplug
the control box, then unplug the junction box connection
on the boom. Wait 5 seconds and then reconnect the
junction box and then the control box.
If the control or junction box is replaced, you will need
to pair the new control box and junction box together.
This is achieved by plugging in the junction box
connection on the boom, then plug in the control box in
the cab. Then press and hold the ON & OFF buttons
at the same time. The software will search for the new
box and the blue bluetooth light will illuminate once a
connection is made.
FITTING THE CONTROL BOX ONTO THE LOADER
The control box is supplied with a suction cup
attachment. This should be fitted in the cab in a
suitable position that is convenient to the operator on a
smooth, clean dust free surface.
The control box requires a 12v supply and is shipped
with a cigarette lighter plug as standard.
If the supply cable is connected with the wrong polarity
the control box will not switch on.
PREPARATION OF THE TELEHAWK
Position the appropriate loader brackets on the rear
80mm x 80mm beams of the Telehawk, checking they
are correctly positioned centrally to your loader. Tighten
the clamping U bolts to a torque rating of
149 Nm (110 ft
lb).
Fit the appropriate hydraulic fittings to the supply and
return hoses that match the fittings on the loader.
FITTING THE TELEHAWK ONTO THE LOADER
Attach the Telehawk to the loader headstock engaging
the locking mechanism to prevent the machine
detaching. Connect the hydraulic hoses and the power
lead for the electronic controls.
Carefully crowd up and check there is clearance
between the fan motor cover and boom. We recommend
a minimum crowd angle of 45 degrees to allow the
rectangular bale to fall onto the bed chain area.
OPERATION
BALE RESTRAINT BEAM
The bale restraint beam is factory set in the most
desirable position. If problems occur with excessive
operation of the anti blocking system, it may be
advisable to adjust the bale restraint beam forwards
away from the fan to reduce the material feed rate.
SWIVEL CHUTE
The swivel chute rotates through 280 degrees and can
be operated in any position. The material feed
direction is controlled by the chute.
In transport, rotate the chute to point forwards and fully
lower the deflector to keep the width and height of the
machine to a minimum whilst maintaining forward
visibility.
BED CHAIN OPERATION
The valve block includes a flow control valve to vary the
rotational speed of the bed chain.
The bed chain is operated by pressing the bed chain
spreading button, this moves the bale towards the cross
beater. Pressing the same button again will stop the
bed. Pressing and holding the bed chain unloading
button will move the bale away from the cross beater. It
is not necessary to stop the bed chain before pressing
the unloading direction button as this will automatically
cancel the spreading direction before engaging
unloading.
COMMENCING OPERATION
LOADING THE MACHINE
When removing string or netwrap from bales never climb
into the bale chamber unless you, disengage the
hydraulic pump, lower the machine to the ground, apply
the handbrake, stop the engine, remove the key, and
wait for the rotor to come to rest.
The strings or net should be removed from the bale
before spreading, if they are not removed they will wrap
around the cross beater. Putting twine or netwrap
through the machine is not recommended as it will
eventually be spread on the land, polluting future crops.
LOADING RECTANGULAR BALES
If you are using a loader with the driver positioned to the
left hand side of the loading boom and loading direct
from a stack of bales. We recommend starting from the
right hand side and working to the left. This enables the
driver to see the join between two bales. Once the end
of the bale is inside the Telehawk, slightly lift the bale
and continue driving until the bale is in the machine. Do
not force the bale into the crossbeater. This will cause
the machine to go into unblocking mode once the
crossbeater is engaged. Place the chains around the
rear of the bale. Cut and remove the strings.
For easy removal of the strings place the bale on its side
so that the strings are not in contact with the floor.
Do not stand above the machine on a stack of bales to
load the machine manually.
Содержание Telehawk
Страница 1: ...15287 03 19...
Страница 28: ......