Solo Plus Instructions 1-800-782-9927 Version 12-13
Tarm Biomass · 4 Britton Lane · Lyme, NH 03768
The boiler must be installed with the
minimum installation clearances
to combustible materials out-
lined below. Clearances may only be reduced by means approved by the regulatory authorities.
Clearances to Combustibles
Measurement
Minimum Distance
Notes
A-Backwall to Appliance
18‖
Minimum Distance
B-Sidewall to Appliance
8‖
Minimum Distance
C-Sidewall to Appliance
21‖
Minimum Distance on left or right side to allow clear-
ance for Cleaning and Maintenance Tasks.
D-Front of Appliance
36‖
Required Distance for Cleaning the Boiler.
E-Ceiling to Appliance
18‖
Required Distance for Cleaning the Boiler.
F-Combustibles to Pipe
18‖
Minimum Distance
Boiler Installation & Start-up > Locating the Boiler
Page 10
A
B
C
F
B
D
E