Actionair DWFX-C Installation Guide
Comments:
Rev:
Drawn By:
S. Wehrle
Approved By:
Kimberley.M
1 of 1
Reference No:
Gore.S
Date:
Date:
By:
Date:
13/04/2022
25/07/2013
13/04/2022
Date:
H
Checked By:
Sheet
Rev
AAF10730
Description:
If your proposed installation details differ from
that shown here, please discuss this with the
authority having jurisdiction, referencing this
documentation.
Deviation from this drawing requires approval
of the relevant authority.
Connecting ductwork omitted for clarity.
Ductwork must be independently supported.
There must be an appropriate break-away
joint between the damper and the connecting
ductwork on both sides of the installation.
A minimum of 200mm between fire dampers
installed in separate ducts and 75mm between
fire damper and construction elements/edges
needs to be observed unless otherwise
specified in the drawing.
Installation Detail
Stone wool min 33kg/m³
12.5mm gypsum fire
boards type F (EN520)
C
EC1770
MJB 20-02-18
Damper Size Range (mm)
VERTICAL APPLICATION
SMOKE SHIELD DWFX-C IN
PLASTERBOARD WALL AGAINST
SUPPORTING CONSTRUCTION
200 x 200 to 1000 x 1000
VERTICAL BLADES;
Damper can be installed with the blades in
the vertical orientation with the actuator
mounted at the bottom, refer to drawings
for cleat locations; standard DWFX-C =
AAF/0244DWFX-C actuator at bottom =
AA-SS-2001
D
EC1830
RTC 20/03/18
E
EC1919
MJB 27-03-19
F
ECN1922
MJB 03-04-19
A
Stone wool min 30kg/m³
12.5mm gypsum fire
boards type F (EN520)
Stone wool min 30kg/m³
G
ECN5134
MJB 05-02-21
© Swegon Air Management Limited
South Street, Whitstable, Kent CT5 3DU
Tel: +44 (0)1227 276100
Email: [email protected]
www.swegon.com/uk
Please refer to the DoP
for latest classifications
for CE/UKCA
compliance and the
Installation, Operation
and Maintenance Guide
SCAN ME
H
ECN2227
JPM 13/04/22
Vertical Damper Installation in a
Plasterboard Wall against a Floor Slab
Actionair SmokeShield PTC - [AA/F 10730]
Actionair FireShield - [AA/F 11682]
Installation Method
1. Apply a bead of low pressure intumescent mastic
along top edge of damper as a gap filler and Install
the damper against the floor slab and fasten using fire
rated steel fixings and a washer.
2. Frame out the damper using tracks and studs lined
with board. This is done with two vertical lined studs as
close to the damper as possible (outside the cleats) and
a lined cross track below the damper between the two
vertical studs and back fill with mineral/stone wool.
3. Build the partition to the track and stud framework,
coming as close to the damper as possible.
4. Insulate the wall with mineral/stone wool.
5. Seal the damper to the partition with intumescent
sealant and add pattresses to both sides down to the
damper spigot, seal to the damper spigot with intu-
mescent sealant. Fasten the pattresses with drywall
screws at 300mm centres on the sides and bottom
such that they will allow screws to pull into the stud
and track around the hole. Fix the top pattress into the
track at the sides.
6. Finish the wall as standard practice.
7.
A minimum of 200 mm between fire dampers installed
in separate ducts.