2.4 Installing the Server into the Rack
After the rails are attached to both the chassis and the rack:
1. Line up the rear of the inner rails with the front of the rack rails.
2. Slide the chassis rails into the rack rails, keeping the pressure even on both sides (you
may have to depress the locking tabs when inserting).
3. When the server has been pushed completely into the rack, you should hear the locking
tabs "click".
4. Finish by inserting and tightening the thumbscrews that hold the front of the server to
the rack.
Locking Tabs:
The inner rails have a locking tab It locks the server in place when fully
extended from the rack. This prevents the server from coming completely out of the rack
when you pull it out for servicing. If you need to remove the server completely, depress the
locking tabs on each side as you pull it out.
Warning:
Do not pick up the server with the front handles. They are designed to pull
the system from a rack only.