FatTwin F619P2/3-FT User's Manual
20
Note:
Insert the nodes into the chassis from the bottom left to bottom right and then up all
the way to the top (left first, then right). Do not insert the nodes on one side fully (leaving one
side empty) and then the other side or it will be very hard to insert the last node.
Circuit Overloading
Consideration should be given to the connection of the equipment to the power supply circuitry
and the effect that any possible overloading of circuits might have on overcurrent protection
and power supply wiring. Appropriate consideration of equipment nameplate ratings should
be used when addressing this concern.
Reliable Ground
A reliable ground must be maintained at all times. To ensure this, the rack itself should be
grounded. Particular attention should be given to power supply connections other than the
direct connections to the branch circuit (i.e. the use of power strips, etc.).
To prevent bodily injury when mounting or servicing this unit in a rack, you must take
special precautions to ensure that the system remains stable. The following guidelines
are provided to ensure your safety:
•
This unit should be mounted at the bottom of the rack if it is the only unit in the rack.
•
When mounting this unit in a partially filled rack, load the rack from the bottom to the top
with the heaviest component at the bottom of the rack.
•
If the rack is provided with stabilizing devices, install the stabilizers before mounting or
servicing the unit in the rack.
Содержание FatTwin F619P2-FT
Страница 1: ...USER S MANUAL Revision 1 0a FatTwin F619P2 FT F619P3 FT...
Страница 7: ...7 Appendix C System Specifications Appendix D UEFI BIOS Recovery Appendix E BSMI Safety Warnings...
Страница 146: ...142 SuperServer F619P2 3 FT User s Manual 100 127 V 12 9 5 A 60 50 HZ 200 240 V 10 9 8 A 60 50 HZ 150 3 150 3...