62
6. COMMISSIONING
6.1. Start-Up / Shutdown Procedure
The inverter must be installed by a qualified / licensed electrical engineer in accordance with the country's
wiring regulations.
Before switching on, the installation engineer must have completed the Earth Bond, RCD and earth leakage
tests, checked that the solar panel Voc voltage does not exceed 480V and checked the battery voltage.
Power ON Sequence:
1. Switch on AC
2. Press Start Button
3. Switch on Battery and battery breaker
4. Switch on the DC (PV Isolator)
Shutdown Sequence:
1.
Switch off AC
2. Press the start button
3.
Switch off the battery and the battery breaker
4.
Switch off the DC (PV isolator)
6.2. Information for Commissioning the Inverter
After you have successfully powered up the inverter, it must be programmed and set up as per the
programming feature above.