4 Commissioning
Before starting the PCS, make sure all installation and connections are
completed and verified.
If all of the items mentioned above meet the requirements, proceed as follows
to start up the PCS for the first time.
Step 1
Make sure all the above-mentioned items meet the requirements.
Step 2
Close the external AC circuit breaker.
Step 3
Rotate the BAT.
switch to the “ON” position.
Step 4
Use iSolarcloud App to restore the factory settings to the machine.
Step 5
If the PCS needs to communicate with the BMS, use the APP to
configure the BMS data source to be a battery. Otherwise, configure the
BMS data source to be EMS. See User Manual
“10.9 Configuring BMS
Data Sources
” for detailed steps.
Step 6
Use the iSolarcloud App to establish the communication connection with
the PCS through Bluetooth to set the initial parameters. When the device
is initialized, send start instructions via the App For details, please refer
to User Manual
“10.4.2 Login Steps”.
Step 7
The PCS will feed AC power to the grid and enters into the running state.
Step 8
Observe the status of LED indicator panel.
LED indicator
LED state
Definition
Steady Blue
The device is connected to the grid and
operating normally.
Flashing
blue
(fast)
The Bluetooth communication is connected
and there is data communication
.
No fault
occurs.
Flashing
blue
(slow)
The DC or AC side is powered on and the
device is in standby or startup state (not
feeding power into the grid).
Steady Red
A fault occurs and the device cannot
connect to the grid
Flashing Red
The Bluetooth communication is connected
and there is data communication
.
Fault
occurs.
OFF
Both the AC and DC sides are powered
down.