Begin the installation by moving the front corner wall panel into 
position against the back corner wall panel. The two panels 

should lap as shown in Figure 1.

WALL AssembLy

Figure 1

Attach the side wall channels to both the top and bottom of the 
corner wall using two plain rivets. The longer lip of the channel 
should face the inside of the shed (Figure 2). Repeat both this 
step and the previous step for the opposite wall.

Figure 2

Measure and mark the position of the shelves to suit your ideal 
height and spacing requirements, ensuring that the shelves are 

square using a level. The shelf position does not have to be mirrored 

by the opposite side, a staggered layout may best suit your needs. 
Fix the shelves to the inside of the wall panels with colour rivets 
(rivet passing through from the outside of the shed) (Figure 3).

Figure 3

The doorway channels are fixed to the edge of both of the front 

walls (adjacent to the proposed door) with two plain rivets (figure 4). 

Lap the two assembled sides of the locker to the back centre wall 
panel. Ensure the sheets lap as shown in Figure 5.

Figure 4

Figure 5