2.3
Board connection
Figure 5.
STEVAL-GLA001V1 evaluation board connections
•
J100: connect mains voltage input, complying with Line and Neutral connection and operating voltage (refer
to
•
J101, J102 and J103: connect directly the load between the two points, complying with the load capability
(refer to
Section 1.7 AC switch load capability
).
•
via the supplied ribbon cable.
•
J202: connect to external microcontroller (if you do not use the NUCLEO-F030R8) with 5 V and 3.3 V,
complying with power supply output capability (refer to
Section 1.2 STEVAL-GLA001V1 evaluation board
•
J200: supplies insulated low voltage 5 V and 3.3 V power (if required), complying with power supply output
capability (refer to
Section 1.2 STEVAL-GLA001V1 evaluation board main blocks
2.4
1.
Caution: Do not connect mains voltage.
STEVAL-GLA001V1 evaluation board start-up
Follow this procedure below to start the
evaluation board.
Step 1.
Ensure SW100 switch is in the OFF position.
Step 2.
Set the SW200 jumper:
–
development board or 3.3 V external microcontroller
–
to 5 V for 5 V external microcontroller
UM2304
Board connection
UM2304
-
Rev 3
page 6/46