Mounting instructions for multiplay „silva 3“
Item-No. 51 5522 601
© stilum GmbH, Gewerbegebiet Larsheck, D-56271 Kleinmaischeid • Tel. +49 (0) 2689 92790-0 • All rights and product modifications reserved.
1. Select the location of the play equipment taking into account the required
minimum space (see diagram 5).
Note:
Due to possible overheating, do not
place the slide surface southernly.
2. The impact area of a playground equipment with an enforced movement is
not allowed to overlap the impact area of other equipment.
According to DIN EN 1176-1, 4.2.8.5.2 shock-absorbing floors must be made
on the entire impact area of every equipment that cause forced movement.
3. Carry out excavation work for the foundations as shown in diagram 2a and
2b. After excavation compress the foundation floor.
Note:
The combination equipment is installed at play level. Pay attention to
items marked „play level” at play equipment!
4. Set up the concrete foundations according to diagram 2 with central, horizon-
tal reinforcement.
5. After a setting period of 10 – 14 days, depending on weather conditions and
foundation size, fill up and compress the holes between the foundation and
the foundation hole with excavation.
6. Clean the surface of the foundations and start with the installation of the play
equipment.
7. Place the high posts (wendy house 1 and 2) as described in diagram 2b on
the foundations.
Note: Do not screw the base plates onto the foundations yet!
5804
1591
450
1456
992
3272
2802
4562
2320
OHNE SCHRIFTLICHE ZUSTIMMUNG DER KAISER GMBH DARF DIESE
TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT, NOCH DRITTEN MITGETEILT ODER
ZUGÄNGLICH GEMACHT WERDEN, NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VER-
WENDET WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.
1
silva3
Benennung
Gepr.
Blatt
Datum
Projekt
Gez.
Zeichnungsnummer
1:35
A3
Name
Name
Fundamentplan
1018-00-00
Maßstab
Behnke
24.03.17
Gewerbegebiet Larsheck
56271 Kleinmaischeid
Deutschland
Beton
concrete
gewachsenes Erdreich
natural ground
Legende
stoßdämpfender Boden
shock-absorbing floor
C stoßdämpfender Boden
25.08.20 ES
B Balancet.,Haus verschoben 16.12.19 ES
ES
15.02.18
Standfüße gedreht
A
Datum
Änderung
Rev
5804
1591
450
1456
992
3272
2802
4562
2320
OHNE SCHRIFTLICHE ZUSTIMMUNG DER KAISER GMBH DARF DIESE
TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT, NOCH DRITTEN MITGETEILT ODER
ZUGÄNGLICH GEMACHT WERDEN, NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VER-
WENDET WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.
1
silva3
Benennung
Gepr.
Blatt
Datum
Projekt
Gez.
Zeichnungsnummer
1:35
A3
Name
Name
Fundamentplan
1018-00-00
Maßstab
Behnke
24.03.17
Gewerbegebiet Larsheck
56271 Kleinmaischeid
Deutschland
Beton
concrete
gewachsenes Erdreich
natural ground
Legende
stoßdämpfender Boden
shock-absorbing floor
C stoßdämpfender Boden
25.08.20 ES
B Balancet.,Haus verschoben 16.12.19 ES
ES
15.02.18
Standfüße gedreht
A
Datum
Änderung
Rev
5804
1591
450
1456
992
3272
2802
4562
2320
OHNE SCHRIFTLICHE ZUSTIMMUNG DER KAISER GMBH DARF DIESE
TECHNISCHE UNTERLAGE WEDER VERVIELFÄLTIGT, NOCH DRITTEN MITGETEILT ODER
ZUGÄNGLICH GEMACHT WERDEN, NOCH IN SONSTIGER WEISE MISSBRÄEUCHLICH VER-
WENDET WERDEN. ZUWIDERHANDLUNGEN WERDEN URHEBERRECHTLICH VERFOLGT.
1
silva3
Benennung
Gepr.
Blatt
Datum
Projekt
Gez.
Zeichnungsnummer
1:35
A3
Name
Name
Fundamentplan
1018-00-00
Maßstab
Behnke
24.03.17
Gewerbegebiet Larsheck
56271 Kleinmaischeid
Deutschland
Beton
concrete
gewachsenes Erdreich
natural ground
Legende
stoßdämpfender Boden
shock-absorbing floor
C stoßdämpfender Boden
25.08.20 ES
B Balancet.,Haus verschoben 16.12.19 ES
ES
15.02.18
Standfüße gedreht
A
Datum
Änderung
Rev
Diagram 2a: Foundation plan
Reinforcement plan:
Concrete foundation with reinforcement
Foundation: BSt 500S
Stirrups Ø 8 mm lengthwise and cross
Concrete cover h´= 3 cm
Concrete quality class C20/25 – C25/30
play level