background image

581-218 8’ PRIMARY BIPOD SWING 

Installation Guide 

 

 

 

12 

Step 3: Post & Component Installation 

1.

 

We recommend installing the posts once the post are square and level 
you may add the concrete (concrete with a minimum of 2,500 psi should 
be used).  Mix concrete per manufacturers instructions and let it cure for 
at least 24 hours before continuing. 

2.

 

NEVER LEAVE THE INSTALLATION SITE UNATTENDED 
WITHOUT ROPING OFF THE AREA AND EQUIPMENT, 
INSTALLING ALL HARDWARE, SECURING TOOLS AND 
EQUIPMENT, AND COVERING OPEN HOLES WITH A RIGID 
MATERIAL (PLYWOOD).  CHILDREN WILL TRY TO USE 
THE EQUIPMENT EVEN THOUGH ITS NOT FULLY 
ASSEMBLED.  YOU MUST TAKE ACTION TO PREVENT 
INJURY AND DAMAGE.

 

Step 4: Concrete 

1.

 

Verify all swing posts and fittings are tight, level and square.  Once the 
unit is verified to be level and square you may start installing concrete.  
You must use concrete with a minimum of 2,500 psi. 

2.

 

Always pre mix the concrete to the manufactures directions before 
pouring it into the hole.  Never put dry concrete in the hole.  Typically 
each main posthole requires two 80-pound bags of concrete. 

3.

 

Allow concrete to set in accordance with manufacturers directions.  Fill 
holes too about 2” below the surface with concrete.  Once the hole has 
been filled with concrete, slope the top of the concrete down and away 
from the post to keep water from seeping between the post and the 
concrete. 

4.

 

Secure playground area to prevent access while the concrete is setting 
for a minimum of 48 hours. 

5.

 

SportsPlay recommends having a CPSI (certified playground safety 
inspector) present during installation.  If that’s not possible you should 
have the completed playground (after surfacing is in place) inspected by 
a CPSI. 

Step 5: Last Step 

1.

 

After concrete has completely set, backfill all holes with dirt. 

2.

 

Install surfacing.

Содержание 581-218

Страница 1: ...18 8 PRIMARY BIPOD SWING Installation Guide 1 INSTALLATION INSTRUCTIONS 581 218 8 PRIMARY BIPOD SWING Please read the entire manual before beginning installation 1 CTN 5 PIPE 6 TOTAL PCS 146 WEIGHT CLASS 70 ...

Страница 2: ...D SWING Installation Guide 2 TAB SECTION INDEX 1 3D AND 2D DRAWINGS 2 INSTALLATION GUIDE 3 INSTALLATION STEPS 4 COMPONENT INSTALLATION 5 APPENDIX 6 ORIGINAL COMPONENT MAINTENANCE FORMS 7 COMPLETED COMPONENT MAINTENANCE FORMS ...

Страница 3: ...ING 10 SITE REQUIREMENTS 10 MAINTENANCE 10 PLAY AREA 10 Installation Punch List Error Bookmark not defined Footing Layout Example Error Bookmark not defined Step 1 Layout 11 Step 2 Holes 11 Step 3 Deck Post Component Installation 12 Step 4 Concrete 12 Step 5 Last Step 12 Four Hole Bracket Panel Bracket Installation Error Bookmark not defined Other Installation Tips 13 SUPERVISION GUIDE 14 HARDWARE...

Страница 4: ...581 218 8 PRIMARY BIPOD SWING Installation Guide 4 ...

Страница 5: ...581 218 8 PRIMARY BIPOD SWING Installation Guide 5 ...

Страница 6: ...ure and sunlight SportsPlay recommends carefully unpacking the unit and taking an inventory before storing the equipment Care should be taken with all powder coated and thermoplastic coated parts to prevent damage to the coating You have 30 days from receipt of your equipment to file a claim for missing or damaged parts Before you begin Review your playground footing and top view drawings to ensur...

Страница 7: ...nstalled on vertical posts as per ASTM F1487 Instructions for the placement of these labels are included in the appendix of this booklet SportsPlay will provide manufacturer identification labels that must be installed on the structure during installation per ASTM F1487 Installation instructions for these labels are included in the appendix of this instruction manual Labels must be replaced when t...

Страница 8: ...tion and Public Affairs Washington DC 20207 USA Call 1 800 638 2772 US and Canada only Call 301 504 0990 Direct Link http www cpsc gov For a copy of either the standard for surfacing ASTM F1292 or for play equipment ASTM 1487 write to American Society for Testing and Materials 100 Bar harbor drive West Conshohocken PA 19428 2959 USA Call 618 832 9585 Web Site www astm org You must consider the typ...

Страница 9: ...ole digger Wheelbarrow Large construction bar 5 Claw hammer Large dead blow rubber hammer Small sledgehammer to use in blocking the posts Strong and sturdy step ladders Extension cords power supply Levels Magnetic torpedo and 4 long levels Scrap lumber to use for shims in post holes to keep posts level Blocking materials for the post holes bricks concrete blocks etc Files and sand paper Safety sur...

Страница 10: ...closed immediately A maintenance section is included in the appendix of this instruction booklet If a part is missing or damaged the playground must be put out of service while the part is replaced Lack of maintenance will result in premature wear reduced life expectancy and possiblefailure that mayresult in injury All SportsPlay Equipment play events have been engineered to meet all applicable sa...

Страница 11: ...xt page 2 Once the structure is in the desired location within the play area mark the locations of the post by inserting a stake into the center of each post location see drawing below for an example If using spray paint to mark location please be careful not to spray the post 3 Match the post location marks with the footing layout in the front of this booklet Dig your holes using the main post fo...

Страница 12: ...re you may start installing concrete You must use concrete with a minimum of 2 500 psi 2 Always pre mix the concrete to the manufactures directions before pouring it into the hole Never put dry concrete in the hole Typically each main posthole requires two 80 pound bags of concrete 3 Allow concrete to set in accordance with manufacturers directions Fill holes too about 2 below the surface with con...

Страница 13: ...are at some point you may want to apply lubricating oil to the hardware Stainless steel hardware has a tendency to seize so if you are planning on removing the hardware you may want to apply lubricant to prevent this Unless specified in the specific component instruction step do not tighten the hardware completely until the entire unit is assembled ...

Страница 14: ...broken equipment Do not allow children to play on broken equipment or equipment with missing components Make sure there are no unsafe modifications especially ropes tied to equipment Remove all unsafe modifications and close the equipment for play until they are removed Keep children in the designated play area Do not let children play on wet equipment Prevent overcrowding on play equipment Loose ...

Страница 15: ...BIPOD SWING Installation Guide 15 X SET SCREW D SHACKLE 2 3 8 SWING HANGER 5 16 X 1 BUTTON HEAD NUT 5 16 X 2 BUTTON HEAD BOLT 5 16 LOCK WASHER 3 16 ALLEN WRENCH YELLOW BAG ALLEN WRENCH BLUE BAG 5 16 ALLEN WRENCH RED BAG ...

Страница 16: ...581 218 8 PRIMARY BIPOD SWING Installation Guide 16 COMPONENT INSTALLATION INSTRUCTIONS ...

Страница 17: ...uired MAINTENANCE As the owner of the playground you are responsible for maintenance of the equipment and play area A maintenance schedule must be developed and the equipment inspected frequently A maintenance section that includes component specific maintenance requirements is included at the end of this manual Be sure to inspect surfacing for foreign objects that could cause injury and that suff...

Страница 18: ...x 5 6 Long 4 7 342 506 D Shackle 8 8 196 802 x Socket Set Screw 10 9 116 545 5 16 x 2 Button Head Bolt 2 10 216 512 5 16 x 1 Button Head Nut 2 11 326 501 5 16 Lock Washer 2 12 105 017 2 3 8 Alum Pipe Plug 2 13 416 350 3 16 Socket Key 2 14 416 500BPK 5 16 Scocket Key 1 15 416 400 Socket Key 2 16 805 532 Warning Label 1 17 805 534 SportsPlay Label 1 18 516 400 Locktite 1 NOTE Keep a copy of these in...

Страница 19: ...he bottom of the support post or slide leg on a suitable flat blocking material to prevent it from sinking further into the soil We recommend you use a brick block of wood or several inches of gravel The footing depth does not include this blocking material since materials used often vary It is the owner installers responsibility to check local building codes and to comply with those codes All foo...

Страница 20: ...March 2 2016 4 581 218 8 PRIMARY BIPOD SWING INSTALLATION INSTRUCTION ELEVATION AND FOOTING LAYOUT VIEW ...

Страница 21: ...to take them out to make an adjustment It is recommended that you add a drop of oil to bolts that may have to be removed before you install them Do not tighten bolts all the way until the unit is completely assembled and all components are square and level Identify and separate all parts by referencing the detail drawings and the parts list As you unpack and separate the components use the cardboa...

Страница 22: ...pproximately correct position Assemble swing frame on side on ground If more than one section assemble section by section __4 Attach Swing End to Legs To do this you will need four 1 7 8 x 11 pipe 2 two swing end fittings 1 Place the swing legs into the swing end fittings See Detail A __5 Attaching Middle Post to Swing End You will need one 2 3 8 x 11 pipe 11 two 5 16 x 2 button head bolts 9 two 5...

Страница 23: ...ng holes may be marked out and dug from footing layout however it is easier to position swing in proper location mark holes move swing aside and dig holes __9 Stand swing upright onto legs and brace in footing holes so that 2 3 of pipe will be under intended level of resilient surfacing and the top rail is at desired height Plumb and level entire unit Tighten all set screws __10 Once the entire pl...

Страница 24: ... has set back fill dirt over the footing holes inspect the area and components for tools hazardous debris and sharp edges Verify all components are installed and all hardware is tight and then install the safety surfacing __12 Inspect the components for sharp edges and if necessary file them down and apply touch up paint ...

Отзывы: