HP10 Series 1-Phase
AC EV Charging Station
User Manual
- 20 -
Drill 4 holes with diameter of 10mm and depth of at least 50mm on the wall with spacing of 143mm
× 152mm, and secure the accessories-D to the wall with expansion screws.
Step 2: Wiring
As shown in Fig. 5-6, unscrew the total 6 screws with mark [A] to open the front cover of wallbox
before wiring; no need to unscrew the 4 screws with mark "×".
[A]
Screw
[B]
Gland of input cable
[C]
Charging cable
[D]
Main board
[E]
Terminals of input power
[F]
Input power cable
[G]
Lever of terminal
[H]
Wire conductor
Fig. 5-6 Open the wallbox and wiring
Loosen the gland [B], pass the prepared power cable through it.
Remove 10~12 mm of insulation from the wire conductor [H].
Pull up the lever [G] to open the terminal, plug the wire conductors into each terminal,
press down the lever[G] to make sure every wire conductor is reliable connect with
terminal.
Screw the total 6 screws with mark [A] to reset the front cover of wallbox.
Tighten the gland of input cable.
Step3: Fixed the wallbox
Fig. 5-7 Mounting the wallbox on the accessories-D