Soltaro AIO2-INS Series Скачать руководство пользователя страница 1

 

 
 

Operating Manual 

AIO2-INS Series 

 
 

 

 
 
 
 
 

 

Содержание AIO2-INS Series

Страница 1: ...Operating Manual AIO2 INS Series...

Страница 2: ...1 Version DM AIO2 INS EN 1 1...

Страница 3: ...ith AIO2 BTLV 5KWH battery 14 5 3 Mounting the Inverter with AIO2 BTLV 10KWH battery 18 6 Electrical Connection 23 6 1 Wiring Diagram 23 6 2 Wiring Diagram 24 6 3 Overview of the Connection Area 25 6...

Страница 4: ...fety precautions and general information symbols are used in this manual These important instructions must be followed during installation operation and maintenance of the inverter Indicates a hazard...

Страница 5: ...roperty damage and to ensure long term operation of the product please read and follow all the instructions and cautions on the inverter and this user manual during installation operation or maintenan...

Страница 6: ...ut authorization otherwise the warranty commitment for the inverter will be invalid Appropriate methods must be adopted to protect inverter from electrostatic discharge any damage caused by ESD is not...

Страница 7: ...4 3 Scope of Delivery A B C D E F G H 1 2 3 4 5 6 7 8 I J K L M N Item QTY Designation A 1 Inverter B 1 Wall Mounting Bracket...

Страница 8: ...E 1 EPS Connector Amphenol or Wieland F 1 Grid Connector Phoenix or Wieland G 2 PV Connectors Amphenol HC4 or Multi Contact MC4 2PV 2PV H 1 WiFi Stick optional I 1 CT and Smart Meter J 3 Terminal Resi...

Страница 9: ...rter are ahead of the field and should be understood prior to install 4 1 View of the Inverter Figure 1 View of the AIO2 INS Series Hybrid Inverter Position Designation A Graphical Display B LED light...

Страница 10: ...Hot Surface Refer to the Operating Manual 5min Danger Risk of Electric Shock due to Stored Energy Cut off all power and wait at least 5 minutes before any work is carried out on the inverter G98 or G9...

Страница 11: ...4 2 Topology of the Inverter Figure 2 AIO2 INS Series Hybrid Inverter topology 4 3 System Diagram kWh PV Array Hyper S Router Internet Loads Smart Meter Billing Meter Mobile APP Grid DC AC Communicati...

Страница 12: ...arged to supply local loads if extra power is required it will be imported from grid When the battery SOC is below the DischargeEndSOC Grid value or fully discharged the inverter will stop working and...

Страница 13: ...out grid the inverter should be working in off grid back up operating mode i When grid or diesel generator is available When the battery is below the DischargeEndSOC Grid value it will be charged firs...

Страница 14: ...o restart several times before shutting down completely Turn off or unplug load to remove the short circuit fault or overload as soon as possible 2 Firmware update may be required to support this mode...

Страница 15: ...wing conditions If it does then a risk assessment will be required No direct sunlight No rain exposure No snow lay up Direct sunlight Rain exposure Snow lay up Additional Notes Unsafe due to assessmen...

Страница 16: ...xample locations where chemicals are processed or stored Exposed to direct sunlight or in an enclosure exposed to direct sunlight Little or no airflow Mounted on a surface without suitable fire heat r...

Страница 17: ...Procedure STEP 1 Drill holes into the wall 12mm drilling depth 65mm The dimensions of the back of the product are as follows note the height of the bottom row of holes 200mm Unscrew the M8 60 expansio...

Страница 18: ...he hanger Note Make sure that the four hooks of the hanger are all engaged otherwise it will not be strong enough STEP 4 Install the outer frame of the wiring area Place the frame of the wiring area o...

Страница 19: ...y the arrows fix the outer frame to the wall STEP 6 Install the inverter hanger use 3 M5 10 Phillips head screws to fix the inverter hanger to the frame of the wiring area The inverter hanger is fixed...

Страница 20: ...ng the inverter on the hanger make sure the four hooks on the side of the rack are engaged to prevent the inverter from falling STEP 8 After the battery and inverter are wired buckle the cover of the...

Страница 21: ...y Procedure STEP 1 Drill holes in the wall 12mm drilling depth 65mm The dimensions of the back of the product are as follows note the height of the bottom row of holes 200mm Unscrew the M8 60 expansio...

Страница 22: ...19 STEP 2 Install the hanger with 6 M8 60 inner hexagonal expansion screws as shown in the picture to the right...

Страница 23: ...t be strong enough STEP 4 Install the outer frame of the wiring area Place the frame of the wiring area on the battery align the outer frame and screw the three M5 10 stainless steel Phillips head scr...

Страница 24: ...the wiring area The inverter hanger is fixed to the wall with 5 M8 60 hex screws STEP 7 Hang the inverter on the hanger make sure the four hooks on the side of the rack have been engaged to prevent th...

Страница 25: ...22...

Страница 26: ...ical installation and maintenance shall be conducted by a licensed electrician and shall comply with Australia New Zealand National Wiring Rules Because the inverter does not maintain neutral integrit...

Страница 27: ...24 6 2 Wiring Diagram Wiring Diagram for Europe...

Страница 28: ...Controllers i Battery Connectors j Additional Grounding Point 6 4 PV Connection Please only use the PV connectors from the accessory box for connection Before connecting please make sure The voltage c...

Страница 29: ...is in the off position Otherwise please use an external PV switch to switch off the PV connection during wiring and when necessary for maintenance Procedure Use IEC61730 class A Rating PV modules When...

Страница 30: ...al AC switch 40A must be used on the Grid connection to cut the inverter off from the Grid when necessary Procedure STEP 1 Assemble the Grid connector Make sure Live Neutral PE wire are correct please...

Страница 31: ...the inverter to power backup loads directly from the grid must be installed Before connecting please check the following The grid voltage and frequency must be in the permissible range External AC sw...

Страница 32: ...t down under full loading with high ambient temperature if grid is absent Accepted loads as below Inductive Load Max 1 5KVA for single inductive load max 2 5KVA for total inductive load power Capaciti...

Страница 33: ...nnection diagram 6 7 2 Battery Power Connection Procedure STEP 1 Please use the pre assembled battery power wire in the accessory box for connection STEP 2 Connect the battery cables to the inverter A...

Страница 34: ...the BMS communication cable in the accessory box is appropriate for the battery If you are not sure please confirm with your battery vendor Procedure STEP 1 Please insert the connector with water pro...

Страница 35: ...onnector STEP 3 Please use the smart meter connector in the accessory box for communication Insert the connector with water proof cap into the port marked MULTI on inverter and fasten the cap STEP 3 T...

Страница 36: ...Fi Stick Connection Procedure STEP 1 Insert the WiFi stick to the EMS port and fasten the nut tight EMS Connector Pin Definition 1 2 3 4 5 6 7 8 L From Grid CT N RS485B RS485A Smart Meter Cable To Inv...

Страница 37: ...DRM Connection DRM is provided to support several demand response modes by certain control signals DRM Connector Pin Definition 1 2 3 4 5 6 7 8 1 DRM1 5 2 DRM2 6 3 DRM3 7 4 DRM4 8 5 3 3V 6 DRM0 7 3 3...

Страница 38: ...een D Battery real time parameters including power voltage SOC and current If the connection to battery is disconnected the icon arrow and data will not be displayed on the screen E Load consumption r...

Страница 39: ...art displaying The icon of grid and its parameters should appear on the screen If not please power off and check for the connections of grid power line and smart meter STEP 2 Power on the Battery The...

Страница 40: ...APP to initiate the self test procedure and get the test results Refer to Soltaro APP Operation Instructions for details 7 3 Decommission STEP 1 Turn off the load STEP 2 Turn off the PV STEP 3 Turn o...

Страница 41: ...R O LOCAL Home Page Parameter Display Settings Inverter List Inverter Status Overview Grid Status EPSStatus Smart Meter Status PV Status BMSStatus Energy Today Energy Total System Status Basic Setting...

Страница 42: ...EP 2 Connect to the inverter Connect the mobile phone or pad to the same wireless network WiFi as the inverter Open the APP click the arrow on the upper right corner of home page Search the inverter I...

Страница 43: ...ick the Basic Settings Write in the password to enter the setting interface This can be accessed by contacting Soltaro STEP 2 Set the country Check the Country make sure it is your current location If...

Страница 44: ...41 7 4 4 Time Synchronization Procedure STEP 1 Enter the Setting interface Go to Settings interface click Inverter Commands STEP 2 Time Synchronization Click Time Date Sync...

Страница 45: ...ation Periods and Parameter Enable the Scheduled Operation Set the operation period and parameters according to your requirements You can also set the discharge period for the EPS mode if necessary Cl...

Страница 46: ...Volt Var mode STEP 3 Power derating for voltage variation Volt Watt mode The inverter power output will vary in response to the AC grid voltage This is switched on by default It can be enabled disable...

Страница 47: ...44...

Страница 48: ...V1 OCPs F1 00000004 PV2 OVP F1 00000008 PV2 OCPs F1 00000010 System generation insufficient F1 00000020 M_PV OCPh F1 00000040 M_Bus OCPh F1 00000080 M_BAT OCPh F1 00000100 Grid Voltage Abnormal Check...

Страница 49: ...1 F1 40000000 S_PV OCPh F1 80000000 S_DC BUS OVP F2 00000001 Grid Grounding Fault Check the grounding wire F2 00000002 L N Reversely Connected Check the L N wire F2 00000004 Insulation Fault Check the...

Страница 50: ...Cell Imbalance F3 00000400 External Comm Smart Meter Communications between Inverter and Smart Meter is not working Check Smart Meter Cabling is connected correctly install 1kohm resistor Check Smart...

Страница 51: ...m output fault current 80A 3ms 80A 3ms 80A 3ms Conditional short circuit current Icc 80A 3ms 80A 3ms 80A 3ms Maximum output overcurrent protection 19 5A 24A 30A 33A Recommended circuit breaker 20A typ...

Страница 52: ...15A 15 15A 15 15A Strings per MPP Tracker 2 1 1 Number of MPP Trackers 1 2 2 Max inverter backfeed current to the arrary 0 A 0 A 0 A Galvanic Isolation for PV Modules Transformerless Battery Input Bat...

Страница 53: ...Altitude Up to 2000m above sea level without derating IP Protection Type IP 65 Protective class Class I Cooling Concept Free convection 9 2 Specification of battery Battery Model AIO2 BTLV 5KWH AIO2 B...

Страница 54: ...50 discharge Dimension 540 430 210 mm 540 680 210 mm Weight 45 kg 85 kg IP Protection Type IP65 9 3 Certificates and Grid Regulations EMC EN61000 6 1 EN61000 6 2 EN61000 6 3 EN61000 6 4 EN61000 4 16 E...