
25
en
6 Commissioning
Follow these steps to start up the inverter:
1. Switch ON the DC isolation switch on the lower part of the inverter (see
2. Switch on the external switch of the AC feed line connecting the inverter to the grid.
3. Observe the status of LED indicators on the inverter according to the table escribed in
.
When the LED ndicators indicate a successful grid connection, the inverter is connected and
ready for operation.
Powering OFF the inverter
To take the inverter out of operation, carry out the following steps:
1. Switch off the circuit breaker at AC terminal.
2. Switch OFF the DC isolation switch on the lower part of the inverter (see
).
10 min
DANGER!
Fatal electric shock hazard!
Components within the inverter are charged with a high voltage
■
Life threatening hazard due to high voltage in the inverter! Dis-
connect the voltage from the inverter. Wait 10 minutes before
opening the inverter.
Содержание 17SHT
Страница 1: ...Instruction Manual SolarMax SHT series 17SHT 20SHT 22SHT 25SHT 28SHT 30SHT...
Страница 4: ...4...
Страница 39: ...39 en...