If not already ON - turn ON AC to the inverter by turning ON the circuit breaker
on the main distribution panel.
Open SetApp and follow the instructions on the screen (scan the inverter bar-
code; move the ON/OFF/P switch to P position (for less than 5 sec) and
release).
The mobile device creates a Wi-Fi connection with the inverter and displays the
main Commissioning screen.
In the main menus, tap the menu red arrows (
›
) to perform the system commissioning
or configuration task. Tap the
Back
arrow (
‹
) to return to the previous menu.
The next sections provide more information about configuration options (in addition to
Country and Language
and
Pairing
Configuring the Installation on page 37).
Setting Country and Language
1. From the Commissioning screen select
Country and Language
.
2. From the
Country
drop-down list, select the required country setting.
WARNING!
The inverter must be configured to the proper setting in order to ensure that
it complies with the country grid code and functions properly with the
country grids.
3. From the
Language
drop-down list, select the language.
4. Tap
Set Language
.
Pairing
1. From the main menu, select
Pairing
.
2. Tap
Start Pairing
.
3. When Pairing Complete is displayed, the system startup process begins:
Since the inverter is ON, the power optimisers start producing power and the
inverter starts converting AC.
WARNING!
When you turn ON the inverter ON/OFF/P switch, the DC cables carry a high
voltage and the power optimisers no longer output a safe output.
Chapter 5: Activating, Commissioning and Configuring the System
38