![SolarEdge SE K Series Скачать руководство пользователя страница 45](http://html1.mh-extra.com/html/solaredge/se-k-series/se-k-series_installation-manual_1313719045.webp)
On-grid Commissioning of the inverter
Step 1: Activating the Installation
During system activation, a Wi-Fi connection is created between the mobile device and
the inverter and the system firmware is upgraded.
Before activation
Download, register (first time only) and login to SetApp on your mobile device.
Verify that the application is updated with the latest version.
If applicable, turn on all devices (battery, Energy Meter) connected to the inverter,
so that the devices may be auto-detected.
To activate the inverter:
1. Turn-on the AC circuit breaker on the main distribution panel.
2. Turn-on the DC Disconnect Switch (if applicable).
3. Open SetApp and follow the on-screen instructions (scan the inverter barcode;
move the ON/OFF/P switch to P position for 2 seconds and release).
SetApp creates a Wi-Fi connection, upgrades the inverter firmware and activates the
inverter.
4. When the activation is complete, do one of the following:
Select
Connect to Another Device
to continue activating additional inverters.
Select
Start Commissioning
for pairing and other system configuration.
Step 2: Commissioning and Configuring the
Installation
This section describes how to use the SetApp menus for commissioning and
configuring the inverter settings.
Menus may vary in your application depending on your system type.
To access the Commissioning screen:
Do one of the following:
During first time installation: Upon activation completion, in the SetApp, tap
Start
Commissioning
.
Three Phase Inverters with Synergy Technology
44
On-grid Commissioning of the inverter
Содержание SE K Series
Страница 74: ......