Snap-on EEWB304B Operators Manual
1.7 DIMENSIONS OF THE MACHINE
Figure 4
- Footprint dimensions.
1.8 REQUIRED INSTALLATION AREA
Make sure that from the operating position the user can
see all of the machine and the surrounding area.
The operator should prevent non authorized persons
and/or objects from entering the area which may cre-
ate potential hazards.
The machine should be installed on a stable level floor.
Do not install the machine on a uneven floor.
If the balancer is to be installed on a raised floor, the
floor must have a capacity of at least 110lbs per sq ft.
(5000 N/m² - 500 kg/m²).
It is not required to secure the machine to the floor.
Install the machine in a dry, covered area.
The installation of the machine requires a working area
of at least 62” x 64.5” (1575 x 1638 mm) (Figure5).
Figure 5
- Recommended work area
1.9 INSTALLATION INSTRUCTIONS
CAUTION! CAREFULLY REMOVE THE BALANCER
FROM THE PALLET.
THE UNIT IS HEAVY AND THE WEIGHT IS NOT
EVENLY DISTRIBUTED.
DO NOT LIFT THE BALANCER BY THE SHAFT.
DROPPING THE UNIT MAY CAUSE PERSONAL IN-
JURY OR EQUIPMENT DAMAGE.
2.0 BALANCER ASSEMBLY
2.1 MOUNTING THE SHAFT ADAPTER
A.
Mount the threaded shaft onto the arbor of the bal-
ancer. Tighten firmly using the supplied wrench. (Fig-
ure 6).
IMPORTANT!
-
CHECK THAT THE SURFACES ARE
PERFECTLY CLEAN AND NOT DAMAGED. AN IN-
CORRECT MOUNTING MAY RESULT IN SIGNIFI-
CANT IMBALANCE.
Figure 6