A. COMPLETING THE INSTALLATION

1. Confirm that all water, gas and electricity are

turned off.

2. Inspect the boiler combustion chamber for foreign

objects and remove if present.

3. Check physical condition of burners and pilot. Make

certain that there are no unusual bends or
perforations in the burners or pilot. Replace
components if necessary.

4. Verify that water piping, venting, gas piping and

electrical wiring and components are installed
properly. Refer back to previous sections of these
instructions as well as equipment manufacturer’s
instructions as necessary.

5. Fill the boiler and system with water, making certain

to vent all air from all points in the system. To check
water level in the system, open and close each vent
in the system. Water should exit from each vent
when it is opened.

6. The pressure reducing valve on the fill line will

typically allow the system to be filled and pressurized
to 12 psi (83 kPa). Consult the valve and expansion
tank manufacturer for more specific information.

7. Check joints and fittings throughout the system for

leaks. If leaks are found, drain the system and repair
as required.

8. Connect a manometer to the gas valve on the valve

outlet (gas manifold). Use the 1/8 NPT tapping
provided.

9. Confirm that the gas supply pressure to the boiler is

above the minimum and below the maximum values
for the gas being used. See the end of Section 5 for
these values. If a supply pressure check is required,
isolate the boiler and gas valve before performing
the pressure check. If the supply pressure is too high
or too low, contact the gas supplier.

10. Turn on electricity and gas to boiler.

11. Light the boiler by following the Lighting/Operating

Instructions label mounted to the jacket panel. The
initial ignition may require several tries as the piping
is purged of air.

12. Use the sequence descriptions in Figures 6.2, 6.3

and 6.4 in Section 6 (Electrical) to follow light-off
and shutdown sequences and to assist in diagnosing
problems. If the boiler does not function properly,
consult Section 8, Troubleshooting.

13. The gas manifold and control assembly are made of

gas-tight, completely factory assembled and installed
components of the base assembly. See Figure 7.1
and 7.2.

INSTALLATION AND OPERATING INSTRUCTIONS

7. START-UP PROCEDURES

20

Содержание GBX 105

Страница 1: ...y drywall dust will cause contamination of theburner resultinginpossibleseverepersonalinjury deathorsubstantialpropertydamage Theboilercanonlybeoperatedwithadust free air supply Follow the instruction...

Страница 2: ...WEEKLY WITH BOILER IN USE 31 D MONTHLY WITH BOILER IN USE 31 E ANNUALLY BEFORE START OF HEATING SEASON 32 10 BOILER DIMENSIONS RATINGS 33 11 REPAIR PARTS 34 A BASE COMBUSTIBLE FLOOR PAN 34 B MANIFOLD...

Страница 3: ...e is known to be between 0 6 and 0 4 air changes per hour If the air infiltration rate is known to be below 0 4 then the Known Air Infiltration Rate Method must be used If the building in which this a...

Страница 4: ...tional spaces that have a total minimum free area of 2 in2 per 1000 Btu hr 44 cm2 per 1000 W of total input rating of all equipment See Figure 1 2 for an illustration of this arrangement 4 Outdoor Com...

Страница 5: ...oor air provided a The size and location of the indoor openings comply with Subsection 3 b The outdoor openings are to be located in accordance with Subsection 4 c The size of the outdoor openings are...

Страница 6: ...s shall not serve both upper and lower combustion air openings where both such openings are used The separation between ducts serving upper and lower combustion air openings shall be maintained to the...

Страница 7: ...ection Pipe the return to the tee Pipe the drain valve nipples and tee to the 1 1 4 NPT return tapping as shown in Figure 3 1 3 Supply Piping Pipe the supply to the 1 1 2 NPT supply tapping at the top...

Страница 8: ...oiler water during the cooling cycle 9 If this boiler is installed above radiation level provide a low water cutoff device either as a part of the boiler or at the time of boiler installation B SAFETY...

Страница 9: ...layouts 2 Run each zone pipe down then up to zone to prevent air accumulation in piping 3 If required provide means to isolate and drain each zone separately INSTALLATION AND OPERATING INSTRUCTIONS Fi...

Страница 10: ...EZE PROTECTION For new or existing systems that must be freeze protected 1 Glycol in hydronic applications is specially formulated for this purpose It includes inhibitors which prevent the glycol from...

Страница 11: ...in vent piping close to the boiler See the Vent Damper Installation Instructions below B VENT DAMPER INSTALLATION GENERAL 1 Do not use one vent damper to control two or more heating appliances See Fi...

Страница 12: ...tch and determine there is no blockage or restriction leakage corrosion and other deficiencies which could cause an unsafe condition c Insofar as is practical close all building doors and windows and...

Страница 13: ...location is shown in Figure 5 1 7 Check piping for leaks Use an approved gas detector a non corrosive leak detection fluid or other leak detection method If leaks are found turn off all gas flow and r...

Страница 14: ...42 1 2 140 56 1 6 175 70 2 0 195 78 2 2 Pipe Length in Feet Meters 3 4 Pipe 1 Pipe 1 1 4 Pipe 1 1 2 Pipe 10 3 0 278 7 9 520 14 7 1050 29 7 1600 45 3 20 6 1 190 5 4 350 9 9 730 20 7 1100 31 1 30 9 1 1...

Страница 15: ...controls 3 This boiler is supplied with safety devices in addition to the limit For a description of these devices and how they work to ensure the safe operation of the boiler see Section 7B 4 If the...

Страница 16: ...h is closed and the flame rollout switch is closed Pilot flame is monitored through the pilot thermocouple If pilot flame is lost during a call for heat main and pilot gas flow will be shut off The va...

Страница 17: ...opens the vent damper b Once the damper is proven open the ignition circuit within the gas valve energizes provided that all of the following conditions are met the blocked vent switch is closed and...

Страница 18: ...18 Figure 6 4 Intermittent Ignition System Operating Sequence INSTALLATION AND OPERATING INSTRUCTIONS...

Страница 19: ...19 INSTALLATION AND OPERATING INSTRUCTIONS Figure 6 5 Zone Wiring with Zone Valves Figure 6 6 Zone Wiring with Circulators...

Страница 20: ...hout the system for leaks If leaks are found drain the system and repair as required 8 Connect a manometer to the gas valve on the valve outlet gas manifold Use the 1 8 NPT tapping provided 9 Confirm...

Страница 21: ...fold and Burner Assembly Standing Pilot Continuous Ignition Figure 7 2 Gas Valve Manifold and Burner Assembly Intermittent Ignition Figure 7 3 Valve Tapping and Adjustment Screw Locations INSTALLATION...

Страница 22: ...22 INSTALLATION AND OPERATING INSTRUCTIONS Figure 7 4 Operating Instructions...

Страница 23: ...URN OFF GAS TO APPLIANCE 8 Find pilot follow metal tube from gas valve The pilot is between two burner tubes Pilot Burner 9 Turn the gas control knob counterclockwise to PILOT 10 Push in red reset but...

Страница 24: ...decrease pressure clockwise to increase pressure Refer to Figure 7 3 for location of gas pressure regulator Replace the cap screw when adjustment is complete 3 In no case should the final manifold pr...

Страница 25: ...s previous setting 2 To check operation of the ignition system safety shut off features a Standing Pilot i Turn the gas control knob counterclockwise to PILOT The main burner should go out and the pil...

Страница 26: ...ough oxygen corrosion pitting 5 Check the expansion tank and automatic fill valve if used to confirm that they are operating correctly If either of these components causes high pressure in the system...

Страница 27: ...must follow all applicable codes and regulations in repair of any boiler problems INSTALLATION AND OPERATING INSTRUCTIONS 8 TROUBLESHOOTING Should overheating occur or the gas supply fail to shut off...

Страница 28: ...upply ventilation and venting system 1 Insufficient pilot flame 2 Pilot burner orifice clogged 3 Overfiring 4 Misaligned burners or pilot 5 Draft problem in boiler room Delayed ignition 1 Increase pil...

Страница 29: ...29 Figure 8 1 Intermittent Ignition System Troubleshooting Sequence INSTALLATION AND OPERATING INSTRUCTIONS...

Страница 30: ...ry Measures Provide adequate ventilation Wear a NIOSH MSHA approved respirator Wear long sleeved loose fitting clothing and gloves to prevent skin contact Wear eye goggles Minimize airborne dust prior...

Страница 31: ...hould never be higher than 5 psi 35 kPa below the rating shown on the safety relief valve 25 psig 172 kPa maximum for a 30 psig 207 kPa rating 45 psig 310 kPa maximum for a 50 psig 345 kPa rating The...

Страница 32: ...n makes a tight seal to prevent leakage of the products of combustion h Re install the top of the jacket vent damper and vent pipe i Re install burners 2 Inspect entire venting system for corrosion su...

Страница 33: ...h mm inch mm inch mm inch mm inch mm inch mm 70 121 2 318 265 8 676 313 8 797 61 4 159 2013 16 529 5 127 105 157 8 403 265 8 676 313 8 797 711 16 195 2013 16 529 5 127 140 191 4 489 265 8 676 313 8 79...

Страница 34: ...ordering parts 11 REPAIR PARTS Table 11 1 Base Combustible Floor Pan 1 2 3 4 Base Assembly Observation Cover Door Base Blanket Seal Combustible Floor Pan Assembly Item No Description 7800 51771 50867...

Страница 35: ...94 50894 Orifice Spud 49 Natural Gas 0 2000 ft 0 610 m elevation specify qty 50895 Orifice Spud 56 LP Gas 0 2000 ft 0 610 m elevation specify qty 50899 50899 50899 50899 Orifice Spud 57 LP Gas 0 2000...

Страница 36: ...m elevation specify qty 50894 50894 50894 50894 Orifice Spud 49 Natural Gas 0 2000 ft 0 610 m elevation specify qty 50895 Orifice Spud 56 LP Gas 0 2000 ft 0 610 m elevation specify qty 50899 50899 508...

Страница 37: ...1 4a Block Draft Hood 12 13 14 Block Assembly Flue Collector Draft Hood Flue Collector Blanket Seal Item No Description 90419 90510 50866 90423 90514 50866 90422 90513 50866 90421 90512 50866 90420 90...

Страница 38: ...n Part Selection Information 70 105 140 175 195 16 Jacket Assembly Complete jacket with insulation and screws 90445 90446 90447 90448 90449 16 16 16 16 16 16 Complete Jacket Consists of Left Side Pane...

Страница 39: ...ge 51324 51324 51324 51324 51324 25 Safety Relief Valve 30 psi Conbraco 10 408 05 50501 50501 50501 50501 50501 Safety Relief Valve 50 psi Watts 350 99950 99950 99950 99950 99950 26 Flame Roll Out Saf...

Страница 40: ...WESTCAST INC 260 NORTH ELM STREET WESTFIELD MA 01085 TEL 413 562 9631 FAX 413 562 3799 www smithboiler com...

Отзывы: