5.   Insert the large port connector 

with its steel inner 

ring into the upper port. 

6.   Insert the two round port connectors into the lower 

ports.

NOTE: Apply the spray adhesive supplied with the 
boiler to the port recess to hold the port connector 
in place if necessary.

7.   Select the correct intermediate section and carefully 

move it into place against the back section, Figure 4. 

CAUTION: Any steam uptake and heater sections 
must be located as shown in Table 3. Failure to 
comply with this caution may result in poor boiler 
performance and prevent the jacket from fi tting!  
Only one intermediate section with an external leg 
boss has been included. It should be located toward 
the front of the boiler for optional low water cutoff 
use. See Table 3.

NOTE: A putty knife or similar tool can be used to 
hold the port connectors in place while the 
intermediate section is positioned. It must be 
removed before the sections make contact or the 
port connector will be damaged resulting in a leak!

8.   Insert the four draw rods through the casting bosses. 

Thread nuts onto one end of the rods.  Place washers 
on the other end of the rods before threading nuts 
onto them see Figure 4. Snug the nuts fi nger tight. 
Use a spirit level to ensure that the fi rst two sections 
are plumb and properly aligned, Figure 6. Check the 
rope to insure that it’s properly positioned. Once the 
sections are plumb and the rope and port connectors 
are properly positioned follow the torque sequence 
shown in Table 4.

Use anti-seize on draw rod and washer, 

coating thread 

and washer on one end only

. Torque the draw rods from 

the end with anti-seize and washer. Follow the steps as 
described below. Do not completely tighten one side; 
gradually work each side using an alternating pattern 
until the correct torque is reached.

Figure 6 - Section Alignment

Table 4 - Section Torque Sequence

    Step 

Rod Position 

    Torque            

 

 

 

        

ft lbs

   

Nm   

 

  1   

Upper Right 

25

 

   

34

  2   

Lower Left 

25

 

   

34

  3   

Lower Right 

25

 

   

34

  4   

Upper Left 

10

 

   

14

  5   

Upper Right 

50

 

   

68

  6   

Lower Left 

50

 

   

68

  7   

Lower Right 

50

 

   

68

  8   

Upper Right 

75

  

 

102

  9   

Lower Left 

75

  

 

102

10  

Lower Right 

75

  

 

102

11  

Upper Left 

30

 

   

42

12  

Upper Right 

125

  

 

169

13  

Lower Left 

125

  

 

169

14  

Lower Right 

125

 

 

 169

15  

Upper Right 

125

  

 

169

16  

Upper Left 

40

  

 

54

NOTE: With these initial torques the sections may 
not be metal to metal, which is acceptable. If any of 
the ports leak during the hydrostatic test the torque 
can be increased to 200 ft lbs, 

271 Nm

 on the upper 

right rod. The torque on the lower left and right rods 
can be increased to 150 ft lbs, 

203 Nm

. Once the 

sections are metal to metal additional torque will not 
improve the seal.

Table 3 - Section Locations

  Boiler 

  Section Location Numbered From Front To Back

 

Model 

1 2 3 4 5 6 7 8 9 10 

11 

12 

13 

14 

15 

16 

17 

18

 

28HE-4 

B       F 

 

Front 

Section

  28HE-5 

 

 

 

 

 

Intermediate Section w/ 5" Tapping & Boss

  28HE-6 

 

 

 

 

H  

Intermediate Section w/ Heater Opening

  28HE-7 

 

 

 

P  

Intermediate Section, Plain

 

28HE-8 

F T H P H T H B      B 

 

Back 

Section

 

28HE-9 

F T H P H P T H B

 

28HE-10 

F H T H P H P T H B

 

28HE-11 

F H T H P T P    T H B

 

28HE-12 

F H T H P T H P H T H B

 

28HE-13 

F H T H P H T P P H T H B

 

28HE-14 

F H T H P H T H P H P T H B

 

28HE-15 

F H T H P H P T H P H P T H B

 

28HE-16 

F H T H P H P H T H P H P T H B

 

28HE-17 

F H T H P H P H T H P H P H T H B

 

28HE-18 

F H T H P H P H P T H P H P H T H B

Содержание 28HE Series

Страница 1: ...any appliance Do not touch any electrical switch Do not use any phone in your building Immediately call your gas supplier from a phone outside of the building Follow the gas supplier s instructions I...

Страница 2: ...llation must be in accordance with the requirements of CAN CGA B149 1 or 2 Installation Code for Gas Burning Appliances and Equipment In the Commonwealth of Massachusetts the installation of a gas bur...

Страница 3: ...re or improper burner operation will occur NOTE Forced make up air supplied to the boiler room must be approved by the local authorities A minimum of 30 ft3 GAL 0 22 m3 L for oil or 20 ft3 100 MBH The...

Страница 4: ...the equipment in the enclosure When ducts are used they must have the same cross sectional area as the free area of the opening to which they connect When calculating the free area necessary to meet...

Страница 5: ...g under positive pressure is connected to a chimney flue never connect a Category I appliance to this flue Doing so can result in the accumulation of carbon monoxide which can cause severe personal in...

Страница 6: ...Never modify or alter any part of the boiler s smoke hood This includes the removal or alteration of any baffles Never install a vent pipe of a diameter different than that of the boiler smoke hood ou...

Страница 7: ...r gas burning appliance to their previous condition of use Une fois qu il a t d termin selon la m tode indiqu e cidessus que chaque appareil raccord au syst me d vacuation est mis l air libre de fa or...

Страница 8: ...e to comply with this warning may result in property damage severe personal injury or death 1 Plug all openings in the boiler and fill it with water 2 Bleed any air off through one of the top tappings...

Страница 9: ...ting thread and washer on one end only Torque the draw rods from the end with anti seize and washer Follow the steps as described below Do not completely tighten one side gradually work each side usin...

Страница 10: ...1 2 in rope that s sticking out around the cleanout opening flush with the castings to insure an air tight seal see Figure 5 3 Install the cleanout cover bolts from the baffled side of the cleanout c...

Страница 11: ...expansion pin item 7 through the hinge bosses to secure the door to the cover 3 Insert the hex bolt item 6 through the hole in the observation port cover 4 Install the spring nut and knob items 3 2 1...

Страница 12: ...mokehood Installation Figure 11 1 Screw the four 5 16 18 x 1 1 2 in studs into the tapped holes around the smokehood opening in the back section 2 Apply smokehood insulation tape to smokehood 3 Place...

Страница 13: ...arrangement for multiple heaters Burner Mounting 1 Clean the burner mounting flange to remove any rust or debris 2 Install the four 3 8 in x 1 1 4 in studs into the tapped holes in the burner mountin...

Страница 14: ...f the ANSI ASME Boiler and Pressure Vessel Code Section IV Also ANSI ASME CSD 1 Standard for Controls and Safety Devices for Automatically Fired Boilers where required All applicable local codes and o...

Страница 15: ...ty of water level controls are available for the 28HE The water column piping needed to properly mount each control is available from Smith Figure 18 shows a typical water column piping arrangement Th...

Страница 16: ...20 3 10 7 40 5 102 386 28HE S 11 2776 810 5 9 22 5 11 9 45 1 113 428 28HE S 12 3040 888 6 5 24 7 13 0 49 2 124 469 28HE S 13 3304 966 7 1 26 8 14 2 53 8 135 511 28HE S 14 3567 1044 7 7 29 0 15 3 57 9...

Страница 17: ...e 17 SERIES 28HE STEAM BOILER INSTALLATION AND OPERATION INSTRUCTIONS Figure 23 Typical Steam Piping Gravity Return for Multiple Boilers Figure 24 Typical Steam Piping Pumped Return for Multiple Boile...

Страница 18: ...be made in accordance with the latest revision of ANSI Z223 1 NFPA 54 Install 3 in nipples into the two 3 in NPT lower tappings in the front section and install ball valves so the boiler can be blown...

Страница 19: ...ted combustion analyzer WARNING Never use an open flame to test for gas leaks Always use an approved leak detection method Failure to comply with this warning can cause extensive property damage sever...

Страница 20: ...ove the bottom heat transfer rod from each flue 3 Replace the cleanout covers and fire the boiler for at least 15 minutes 4 Check the flue temperature If it s greater than 320 F 160 C reseal the clean...

Страница 21: ...ansfer rods in the correct order Figure 7 9 Inspect the cleanout cover insulation and rope seal If damaged or deteriorated replace them 10 Install the clean out covers and reseal them with a silicone...

Страница 22: ...Page 22 SERIES 28HE STEAM BOILER INSTALLATION AND OPERATION INSTRUCTIONS Figure 26 Boiler Assembly...

Страница 23: ...Steam Safety Valve 15 lb 61986 1 1 1 1 1 3 Steam Safety Valve 15 lb 61987 1 19 Back Section 01 3700 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 NS Steam Blank Flange Back 70 1223 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 20 In...

Страница 24: ...es or chimney escaping into the living space Flames coming out around the appliance Yellow colored flames in the appliance Stale or smelly air The presence of soot or carbon in or around the appliance...

Отзывы: