CAUTION: Avoid skin contact with cleaning solution 
to prevent injury! If eye or skin contact occurs fl ush 
with large quantities of water.

NOTE: Some locations do not allow this solution 
to be used. Check with the local authority having 
jurisdiction. 

5.   Mix the cleaning chemicals with water to create a 

concentrated solution. Pour the cleaning solution 
through one of the top tappings in the front section 
and plug it.

6.   Immediately fi re the boiler and maintain a steam 

pressure of 

0 to 2 psig

0 to 13.8 kPa

. It may be 

necessary to cycle the boiler.

WA R N I N G :  M o n i t o r   t h e   b o i l e r   p r e s s u r e 
constantly during the cleaning procedure. Do 
not allow the boiler pressure to exceed 15 PSI, 

103 kPa

 or a discharge of hot water and steam 

will occur!

7.   Adjust the water feed to prevent the build up of 

pressure within the boiler. Continue the skimming 
process until the discharge runs clear.

8.   Shut the boiler off and allow the boiler to cool to 

100°F

,

 34°C

. Remove the skim piping and plug the 

tapping. Open the blowdown valve and fl ush the 
boiler until the discharge runs clear.

9.   Close the blowdown valve and fi ll the boiler with 

water to a level 

1 in.

25 mm

 below the normal water 

level line.

10.  Check the traps and vents for proper operation.

BURNER INSTALLATION

WARNING: The burner must be installed in 
accordance with the burner manufactures 
instructions. Check the boiler rating plate to 
make sure that the boiler is for the type of fuel 
that will be used. If it isn't, do not connect the 
burner to the fuel supply. Failure to comply with 
this warning can result in extensive property 
damage, severe personal injury or death!

Follow the burner manufacturer’s installation instructions 
for the proper installation, fuel piping, wiring, burner 
adjustment and servicing. Mount the burner per the 
instructions on page 13.

When applicable, provisions for vent, bleed and gas 
relief lines must be made in accordance with the latest 
revision of ANSI Z223.1/NFPA 54.

Install 3 in. nipples into the two 3 in. NPT lower tappings 
in the front section and install ball valves so the boiler 
can be blown down.

The feed water requirements for steam boilers at full 
input are shown in Table 9. The addition of water to 
the boiler should be controlled by sensing the actual 
boiler water level. 1 in. NPT water column tappings are 
provided on the front section for the mounting of the 
required water level controls, see Figure 18.

CAUTION: Makeup water connections must be made 
to the return piping and not to the boiler or the 
boiler may be damaged voiding the warranty!

Cleaning of Steam Boilers

The burner must be installed and made operational 
along with the operating, limit and other safety controls. 
The burner on oil boilers must be adjusted to prevent 
sooting of the boiler flues. Final burner adjustment 
should be made after the boiler has been properly 
cleaned.

CAUTION: Failure to properly clean the boiler can 
result in foaming and surging and prevent proper 
operation of the boiler! Boiler damage can occur 
voiding the warranty!

NOTE: Do not connect the boiler to the return piping 
until the system piping has been thoroughly fl ushed 
or recontamination of the boiler can occur.

1.   Plug the 4 in. NPT return tappings in the back 

section and any other unused tappings, see step 5 
below.

WARNING: The safety valve must be installed 
and piped to the fl oor to prevent scalding in 
the event of a discharge, see Figure 16. The 
discharge piping must be sized the same as 
the safety valve outlet. Never install any type of 
valve between the boiler and the safety valve! 
Failure to comply with this warning can result 
in an explosion causing extensive property 
damage, severe personal injury or death!

2.   Fill the boiler with water to a level 

1 in

., 

25.4 mm

 

below the normal water level line of 

50 1/2 in.

1.28 m

 from the fl oor.

3.   Pipe a skimmer off the upper fl ange plate in the front 

section using 1 1/2 in. NPT pipe.

4.   Make a cleaning solution by mixing 

1 lb

0.45 kg

 

each of caustic soda and trisodium phosphate for 
every 

50 ga

189 L

 of water, see Table 7.

Содержание 28HE Series

Страница 1: ...any appliance Do not touch any electrical switch Do not use any phone in your building Immediately call your gas supplier from a phone outside of the building Follow the gas supplier s instructions I...

Страница 2: ...llation must be in accordance with the requirements of CAN CGA B149 1 or 2 Installation Code for Gas Burning Appliances and Equipment In the Commonwealth of Massachusetts the installation of a gas bur...

Страница 3: ...re or improper burner operation will occur NOTE Forced make up air supplied to the boiler room must be approved by the local authorities A minimum of 30 ft3 GAL 0 22 m3 L for oil or 20 ft3 100 MBH The...

Страница 4: ...the equipment in the enclosure When ducts are used they must have the same cross sectional area as the free area of the opening to which they connect When calculating the free area necessary to meet...

Страница 5: ...g under positive pressure is connected to a chimney flue never connect a Category I appliance to this flue Doing so can result in the accumulation of carbon monoxide which can cause severe personal in...

Страница 6: ...Never modify or alter any part of the boiler s smoke hood This includes the removal or alteration of any baffles Never install a vent pipe of a diameter different than that of the boiler smoke hood ou...

Страница 7: ...r gas burning appliance to their previous condition of use Une fois qu il a t d termin selon la m tode indiqu e cidessus que chaque appareil raccord au syst me d vacuation est mis l air libre de fa or...

Страница 8: ...e to comply with this warning may result in property damage severe personal injury or death 1 Plug all openings in the boiler and fill it with water 2 Bleed any air off through one of the top tappings...

Страница 9: ...ting thread and washer on one end only Torque the draw rods from the end with anti seize and washer Follow the steps as described below Do not completely tighten one side gradually work each side usin...

Страница 10: ...1 2 in rope that s sticking out around the cleanout opening flush with the castings to insure an air tight seal see Figure 5 3 Install the cleanout cover bolts from the baffled side of the cleanout c...

Страница 11: ...expansion pin item 7 through the hinge bosses to secure the door to the cover 3 Insert the hex bolt item 6 through the hole in the observation port cover 4 Install the spring nut and knob items 3 2 1...

Страница 12: ...mokehood Installation Figure 11 1 Screw the four 5 16 18 x 1 1 2 in studs into the tapped holes around the smokehood opening in the back section 2 Apply smokehood insulation tape to smokehood 3 Place...

Страница 13: ...arrangement for multiple heaters Burner Mounting 1 Clean the burner mounting flange to remove any rust or debris 2 Install the four 3 8 in x 1 1 4 in studs into the tapped holes in the burner mountin...

Страница 14: ...f the ANSI ASME Boiler and Pressure Vessel Code Section IV Also ANSI ASME CSD 1 Standard for Controls and Safety Devices for Automatically Fired Boilers where required All applicable local codes and o...

Страница 15: ...ty of water level controls are available for the 28HE The water column piping needed to properly mount each control is available from Smith Figure 18 shows a typical water column piping arrangement Th...

Страница 16: ...20 3 10 7 40 5 102 386 28HE S 11 2776 810 5 9 22 5 11 9 45 1 113 428 28HE S 12 3040 888 6 5 24 7 13 0 49 2 124 469 28HE S 13 3304 966 7 1 26 8 14 2 53 8 135 511 28HE S 14 3567 1044 7 7 29 0 15 3 57 9...

Страница 17: ...e 17 SERIES 28HE STEAM BOILER INSTALLATION AND OPERATION INSTRUCTIONS Figure 23 Typical Steam Piping Gravity Return for Multiple Boilers Figure 24 Typical Steam Piping Pumped Return for Multiple Boile...

Страница 18: ...be made in accordance with the latest revision of ANSI Z223 1 NFPA 54 Install 3 in nipples into the two 3 in NPT lower tappings in the front section and install ball valves so the boiler can be blown...

Страница 19: ...ted combustion analyzer WARNING Never use an open flame to test for gas leaks Always use an approved leak detection method Failure to comply with this warning can cause extensive property damage sever...

Страница 20: ...ove the bottom heat transfer rod from each flue 3 Replace the cleanout covers and fire the boiler for at least 15 minutes 4 Check the flue temperature If it s greater than 320 F 160 C reseal the clean...

Страница 21: ...ansfer rods in the correct order Figure 7 9 Inspect the cleanout cover insulation and rope seal If damaged or deteriorated replace them 10 Install the clean out covers and reseal them with a silicone...

Страница 22: ...Page 22 SERIES 28HE STEAM BOILER INSTALLATION AND OPERATION INSTRUCTIONS Figure 26 Boiler Assembly...

Страница 23: ...Steam Safety Valve 15 lb 61986 1 1 1 1 1 3 Steam Safety Valve 15 lb 61987 1 19 Back Section 01 3700 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 NS Steam Blank Flange Back 70 1223 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 20 In...

Страница 24: ...es or chimney escaping into the living space Flames coming out around the appliance Yellow colored flames in the appliance Stale or smelly air The presence of soot or carbon in or around the appliance...