Installation instructions  

EN 1176-1 

 

 

 

 

 

 

 

Maintenance instructions  EN 1176-1 

 
 
 
 
 

03.03.16 

 

 
 
General 

 

The described work is to be carried out by qualified specialists (a minimum of 3 persons). 
Anchoring of the lattice equipment is made on a hot-galvanized square tube frame. Concrete work is not 
necessary  making  any  possible  change  of  location  quite  easy  without  removing  foundations  or  having 
them remain in the earth. 

 
 
 
Dimensions
 

 

 

 

 

Equipment space 

  5,00 m 

Fall space 

     1.50 m 

Minimum space 

  8,90 m 

Height 

    5.00 m 

 
 
 
Age group 

From 4 years of age

 

 

 
 
Number of users 

Approximately 36 children

 

 

 
 
Maximum free fall height 

2.60 m 
 
 
 
 

 
Ground conditions 

 
We refer to EN 1176-1 with respect to the ground conditions in the playing area. Sand, wood chippings, 
gravel  and  synthetic  fall  protector  with  HIC  test  are  accordingly  permitted.  We  recommend  a  400  mm 
thick bed of gravel (grit size 2 – 8 mm) or a sand filling (grain size 0.2 – 2 mm). When applying a synthetic 
fall protector it must be guaranteed that all positions relevant for maintenance (refer to the maintenance 
instructions on Pages 12 and 13) be accessible at all times. If necessary consult SMB. 

 
 
 
 
 

The Skyclimber 

Содержание Skyclimber

Страница 1: ...Fall space 1 50 m Minimum space 8 90 m Height 5 00 m Age group From 4 years of age Number of users Approximately 36 children Maximum free fall height 2 60 m Ground conditions We refer to EN 1176 1 with respect to the ground conditions in the playing area Sand wood chippings gravel and synthetic fall protector with HIC test are accordingly permitted We recommend a 400 mm thick bed of gravel grit si...

Страница 2: ...e parts Page 3 2 3 Alignment of the anchor frame Page 4 3 Assembling the equipment Page 5 3 1 Views of equipment Page 5 3 2 Screwing the lattice equipment together Page 5 4 Space net Page 6 4 1 Unpacking the space net Page 6 4 2 Preassembly of the space net Page 7 4 3 Tensioning the space net Page 7 4 4 Securing the space net Page 8 5 Maintenance instructions according to EN 1176 1 Page 8 5 1 Visu...

Страница 3: ...s Size 24 with angled extension 1 Spanner Size 30 1 Box spanner Size 32 with extension 1 Double ladder approx 2 5 m long 1 Box spanner Size 30 1 Double ladder approx 4 m long 1 Allen key Size 10 with extension 1 Rope pulley 1 Bit for safety screws Recommendation 1 Ratchet with Attachment 32 normal assembly tool 2 Assembly of the anchor frame 2 1 Part description 2 2 Assembly of the anchor frame pa...

Страница 4: ...e are screwed together with the 10 supplied screws M16x85 and nuts This frame must be positioned in the ground at a depth of 470 mm under the playing level Figure 4 and at the same time be aligned horizontally and aligned in diameter With this frame perfect screwing of the frame tubes and the hollow balls is guaranteed Note It is imperative that you observe the positioning of the slide and the ham...

Страница 5: ...limber Seilspielgeräte GmbH Berlin Page 5 Handwerkerstraße 7 15366 Dahlwitz Hoppegarten Phone 49 33 42 50 837 20 Fax 49 33 42 50 837 80 3 Assembling the equipment 3 1 Views of equipment Figure 10 Side view Figure 9 View from the top ...

Страница 6: ...ed to the hollow ball connection K29 with the preassembled nut M20 SIZE 30 which must firstly be completely loosened Insertion of the tensioning cylinder and fork screws into hollow balls of K30 K31 and K32 can be simplified by tension support from the supplied rope When securing the tension nut care must be taken to ensure the correct alignment of the ropes and that they correspond to their run p...

Страница 7: ...his the tension screws for hollow balls K31 and K32 Figures 9 and 10 are made which also mount the tension rope via the fork screws Figure 17 4 3 Tensioning the space net Firstly the aligned connection on the hollow ball K29 is to be solidly secured Tensioning of the space net begins on the hollow balls of K31 and K32 which are screwed to the locking nut Figure 17 using the special spanner supplie...

Страница 8: ... so that our company logo is readable Thank you 5 Maintenance instructions EN 1176 1 5 1 Visual routine inspection The frequency of inspections should be oriented on local conditions high or low amount of use vandalism air contamination weather effects etc The space net and the hammock are to be checked for damage especially breaks in the wire The climber panels as well as the climber grips are to...

Страница 9: ...lock washer between the nuts In order to loosen and secure the tension nut and locking nut M20 Size 32 the bolt M20 can be held with an Allan key Size 10 Figure 16 Finally the open hollow ball is once again closed with the cover Please ensure that the cover is placed evenly so that our company logo is readable Thank you Further re tensioning will be required once or twice more until rope expansion...

Отзывы: