5 Mounting
SMA Solar Technology AG
Operating manual
SI44M-80H-13-BE-en-15
30
1035
742
500
300
300
300
500
1400
Figure 6: Recommended clearances(Dimensions in mm)
5.2
Mounting the Sunny Island
CAUTION
Risk of injury due to weight of product
Injuries may result if the product is lifted incorrectly or dropped while being transported or mounted.
• Transport and lift the product carefully. Take the weight of the product into account.
• Wear suitable personal protective equipment for all work on the product.
Mounting Sunny Island devices with multicluster communication
The multicluster data modules are installed in the master at the factory if multicluster communication has been
ordered. The master can be identified by the labeling on the packaging.
• With multicluster systems, mount the Sunny Island devices with installed multicluster data modules at the
mounting location planned for master devices.
Additionally required mounting material (not included in the scope of delivery):
☐ At least two screws that are suitable for the foundation
☐ At least two washers that are suitable for the screws
☐ At least two screw anchors that are suitable for the support surface and the screws
☐ If the inverter is to be secured against theft, two security screws that can only be unscrewed with a special tool.
Procedure:
1.
CAUTION
Risk of injury due to damaged cables
There may be power cables or other supply lines (e.g., gas or water) routed in the wall.
• Ensure that no lines are laid in the wall which could be damaged when drilling holes.
2. Mark the position of the drill holes using the wall mounting bracket. Use at least one hole on the right-hand and
left-hand side in the wall mounting bracket.
3. Drill the holes and insert the screw anchors.
4. Secure the wall mounting bracket horizontally on the wall using screws and washers.