4.0  XJ-L Busway   Plug-In-Duct (X100, X200, X400)

INSTALLATION INSTRUCTIONS

4.0.1  TO JOIN 2 SECTIONS OF XJ-L BUSWAY:

4.0.1.1

For normal edgewise mounting, the word 

"TOP"

(A) is up. 

(See Fig.1)

4.0.1.2

Loosen screws "B" and remove the external housing 

connectors. 

(See Fig. 1)

4.0.1.3

Assemble the plain end to the insulator end by aligning the 

holes in the housing ends.  Slide the two sections together  
until the housing holes are in line. 

(See Fig. 2)

The joint    

inspection cover must be rotated open. Press the bus bars 
completely into the spring clips.

4.0.1.4

Re-install the external housing connectors so that the guide 

pins engage the holes in the housings and tighten screws "B" 
to 20 IN-LBS.

4.0.1.5

Verify that the bus bars are fully seated in the spring clips. 

4.0.1.6

For X400 busway, install the removable joint clip assembly 

by aligning the assembly over the joint inspection opening 
and pushing it on to the bus bars until it is just below the 
surface of the housing.

TIP: Apply pressure to either side 

of the assembly, left hand and then right hand until fully 
seated.

4.0.1.7

Close joint inspection cover and secure it with provided 

hardware. The joint is now complete.

4.1  Hanger Instructions (XH2, XH3)

4.1.1 TO HANG XJ-L BUSWAY FROM DROP RODS:

4.1.1.1

Position drop rods as required. (Max 10' Spacing). 

4.1.1.2

Using a double nut configuration, assemble the hanger 

halves to each drop rod as shown. 

(See Fig. 3)

4.1.1.3 

Spread the hanger open at the bottom and slip the duct up 

into the hanger.  For normal edgewise mounting, the word 

"TOP"

is up. Secure the hanger with the 1/4-20 hardware.

4.1.2  TO WALL-MOUNT XJ-L BUSWAY:

4.1.2.1

Attach one hanger half to wall as shown. 

(See Fig. 4)

4.1.2.2

Insert duct into hanger.  For normal edgewise mounting, the  

word 

"TOP"

is up.

4.1.2.3

Assemble the hanger complete as shown using the 5/16-18 

hardware on top and the 1/4-20 hardware on the bottom.

4.2  Wall Flange Instructions (WF1, WF2, WF3)

4.2.1

Place the flange halves around the duct where it passes 

through the wall, floor, or ceiling.  Using appropriate 
hardware, attach flanges to wall, floor, or ceiling. 

(See Fig. 6)

3

Figure 1

Figure 6

Figure 4

Figure 3

XH2

XH3

Figure 2

Содержание XJ-L Busway System

Страница 1: ...XJ L Busway Systems Storage Installation and Maintenance Instructions for Piece No 32 J 1010 01 Rev 5 SIEMENS XJ L Busway System ...

Страница 2: ...ect busway components for possible concealed damage from shipping and or handling If damage has occurred file a claim with the carrier If there is no damage restore the packing to its original condition to prepare for job site storage Store busway indoors in a clean and dry area Protect against mechanical damage and exposure to lime dust concrete water corrosive fumes or liquids and salts Failure ...

Страница 3: ...pply pressure to either side of the assembly left hand and then right hand until fully seated 4 0 1 7 Close joint inspection cover and secure it with provided hardware The joint is now complete 4 1 Hanger Instructions XH2 XH3 4 1 1 TO HANG XJ L BUSWAY FROM DROP RODS 4 1 1 1 Position drop rods as required Max 10 Spacing 4 1 1 2 Using a double nut configuration assemble the hanger halves to each dro...

Страница 4: ... 1 1 XJ L Bus plugs are available with molded case circuit breakers or Vacu Break fusible switches Bus plugs may be operated with a pull chain or hookstick from the floor Lightweight and portable plugs are easily moved from one location to another Captive hardware allows for easy removal and re installation 5 1 2 The bus plug contact fingers are lubricated with an oxide inhibiting grease at the fa...

Страница 5: ... busway 5 2 5 Guide the bus plug into the outlet opening ensuring that the bus plug alignment finger and bus plug conductor fingers enter their corresponding openings in the outlet 5 2 6 Push the bus plug firmly into the busway plug in outlet 5 2 7 Make sure the bus plug is fully seated on the busway housing and then tighten all mounting screws 5 2 8 6 and 12 circuit XPMs are provided with drop ro...

Страница 6: ...SE PROCEDURES DO NOT REPRESENT AN EXHAUSTIVE SURVEY OF MAINTENANCE STEPS NECESSARY TO ENSURE SAFE OPERATION OF THE EQUIPMENT PARTICULAR APPLICATIONS MAY REQUIRE ADDITIONAL PROCEDURES SHOULD ADDI TIONAL INFORMATION BE DESIRED OR SHOULD PARTICULAR PROBLEMS ARISE WHICH ARE NOT COVERED SUFFICIENTLY FOR THE PURCHASER S PURPOSES THE MATTER SHOULD BE REFERRED TO THE LOCAL SIEMENS SALES OFFICE OR CALL 1 8...