5 Mounting / Installation
The manual call points are mounted and installed in three steps:
1. Preparation (see the chapter 'Preparation [➙ 27]')
2. Installation (see the chapter 'Installation')
3. Electrical connection (see the chapter 'Installation')
See also
2
Installing the stickers [➙ 36]
5.1 Preparation
Depending on the cabling (surface-mounted cable entry or recess-mounted cable
entry), the housing must be prepared for cable entry.
Manual call points FDM223 and FDM224 (housing FDMH293-x or
FDMH297-R)
1. Push the keyhole cover to the right.
2. Open the door with the key supplied.
3. NOTICE! Keep the key in a safe place.
4. Push the keyhole cover back into place.
5. Determine the cable entry opening(s) in the housing.
–
From above or from below through the cable entry opening provided
–
From the rear through a specified breakout point
a
The manual call point FDM223/FDM224 is now prepared for mounting.
Figure 7: Opening the door of manual call points FDM223 and FDM224
Manual call points FDM223H and FDM224H (housing FDMH292-R)
Cables cannot be inserted though the back of the housing for manual call points
FDM223H and FDM224H. Cables must enter through one of the cable entry
openings provided in the housing.
1. Open the door with the Allen key supplied.
2. NOTICE! Keep the Allen key in a safe place.
3. Determine the cable entry opening(s) in the housing.