R-950A
14
TEST PROCEDURES
PROCEDURE
LETTER
COMPONENT TEST
rectifier, high voltage wire or filament winding of the power transformer is shorted.
CARRY OUT 4R CHECKS.
NOTE: FOR MEASUREMENT OF THE RESISTANCE OF THE RECTIFIER, THE BATTERIES OF THE
MEASURING INSTRUMENT MUST HAVE A VOLTAGE AT LEAST 6 VOLTS, BECAUSE
OTHERWISE AN INFINITE RESISTANCE MIGHT BE SHOWN IN BOTH DIRECTIONS.
CARRY OUT 3D CHECKS.
A. Isolate the high voltage capacitor from the circuit.
B. Continuity check must be carried out with measuring instrument which is set to the highest resistance
range.
C. A normal capacitor shows continuity for a short time (kick) and then a resistance of about 10M
Ω
after
it has been charged.
D. A short-circuited capacitor shows continuity all the time.
E. An open capacitor constantly shows a resistance about 10 M
Ω
because of its internal 10M
Ω
resistance.
F. When the internal wire is opened in the high voltage capacitor shows an infinite resistance.
G. The resistance across all the terminals and the chassis must be infinite when the capacitor is normal.
If incorrect reading are obtained, the high voltage capacitor must be replaced.
CARRY OUT 4R CHECKS.
CARRY OUT 3D CHECKS.
1. If the fuse M10A is blown, there could be shorts or grounds in electrical parts or wire harness.
Check them and replace the defective parts or repair the wire harness.
2. If the fuse M10A is blown when the door is opened, check the 1st. latch switch, 2nd interlock relay
control switch, 2nd interlock relay, monitor switch and monitor resistor.
If the fuse M10A is blown by incorrect door switching, replace the defective switch(es) and the fuse
M10A.
3. If the fuse M10A is blown, there could be short in the asymmetric rectifier or there is a ground in
wire harness. A short in the asymmetric rectifier may have occured due to short or ground in H.V.
rectifier, magnetron, power transformer or H.V. wire. Check them and replace the defective parts
or repair the wire harness.
CARRY OUT 4R CHECKS.
CAUTION: Only replace fuse M10A with the correct value replacement.
D
HIGH VOLTAGE CAPACITOR TEST
E
SWITCH TEST
CARRY OUT 3D CHECKS.
Isolate the switch to be tested and using an ohmmeter check between the terminals as described in the
following table.
Table: Terminal Connection of Switch
Plunger Operation
COM to NO
COM to NC
COM; Common terminal
Released
Open Circuit
Short Circuit
NO;
Normally open terminal
Depressed
Short Circuit
Open Circuit
NC;
Normally close terminal
If incorrect readings are obtained, make the necessary switch adjustment or replace the switch.
CARRY OUT 4R CHECKS.
F
BLOWN FUSE M10A
G
FUSE 20A
CARRY OUT 3D CHECKS.
If the fuse 20A is blown, there is a shorts or grounds in electrical parts or wire harness. Check them
and replace the defective parts or repair the wire harness.
CARRY OUT 4R CHECKS.
CAUTION: Only replace fuse 20A with the correct value replacement.