INSTALLATION AND OPERATION INSTRUCTIONS — FENCE PROTECTION SYSTEMS
18
5
INSTALLATION
General
Installation of the FPS-3 system consists of a systematic installation of dual zone pre-amps, transducer
cable, special fence protection units, such as gate protection, and connection to the FPS-3 Central
Controller.
In general, the installation should proceed as follows:
Step 1
Location and installation of dual zone pre-amps.
Step 2
Installation of sensor cable on fence.
Step 3
Installation of Telegates or other special gate conditions.
Step 4
Connection to Central Controller and MX-5300.
Step 5
Initial testing and adjustment.
Step 6
Final Testing.
Pre-amp Mounting
Once the Fence Protection System has been designed, the approximate location of each dual zone
pre-amp is known. Walking the fence line will allow you to identify the exact location and mounting of
each unit.
The dual zone pre-amps are housed in a moisture proof, EMI and RFI resistant enclosure that may be
directly mounted to a fence post. It is important that the pre-amp be mounted with the connectors
facing down to prevent moisture penetration.
NOTE:
For maximum lightning protection and system noise reduction, each pre-amp
MUST be grounded to a ground rod at the fence, using the 1/4-20 stud located on the
pre-amp housing. Ground rods should be installed in accordance with the National
Electrical Code.
On-Fence Mounting
In most cases, each dual zone pre-amp is mounted directly to the non-threat side of the fence. See
Figure 23.