Installation Notes
SP PRO Installation
The SP PRO must be installed as per the installation instructions in the user manual.
All wiring is carried out in the SP PRO with the exception of the grid L input and the generator L
input wiring. These are wired to the Grid fail-Generator backup kit once it is installed.
Note: For Advanced Multiphase systems, one Grid fail-Generator backup module is installed in
each SP PRO.
When connecting the AC wiring to the SP PRO, please leave enough space for the Grid fail-
Generator backup kit to be installed in the wiring cavity of the SP PRO.
Please note the following:
1.
Backup loads connect into the AC Load L and N terminals in the SP PRO.
2.
Only the L wire from the Grid fail-Generator backup connects into the AC Source L
terminal within the SP PRO.
3.
The Grid L connects to the GRID L terminal on the Grid fail-Generator backup kit. The
Grid N connects to the AC source N on the SP PRO.
4.
The Generator L connects to the GEN L terminal on the Grid fail-Generator backup kit.
The Generator N connects to the AC source N on the SP PRO.
Once the SP PRO has been installed and wired, follow the steps below to install the Grid fail –
Generator backup kit.