Installation Notes
Installing the Grid fail-Generator backup kit into the SP PRO
Referring to the diagram above (page 4), follow the steps below to install the kit.
1.
Fit 2 x 5mm mounting screws to the base of the SP PRO inverter at position
A
. Leave
screws loose.
2.
Fit Grid fail-Generator backup kit to screws as shown. Tighten screws.
3.
Wire the connections from the Grid fail-Generator backup kit to the SP PRO as shown.
NOTE the polarity of the B+ and B- connections
4.
Wire the Generator L and Grid L to the GEN L and GRID L terminals respectively on the
Grid fail-Generator backup kit.
5.
Double check all terminals are tight and clamping the wire only and not the insulation.
Generator Control Wiring
The Generator Run control wiring is wired into the expansion card as shown. This configuration
is for a controller that require two wires to be closed to start and run and then opened to stop
the generator.
In a three phase Advanced Multiphase system the Generator Control Wiring is ONLY connected
to the SP PRO on the L1 phase.
Note: Refer to Tech Note TN0025 for other control options.
SP PRO Configuration – Additional Configuration Settings
The Site Configuration Wizard is used to configuration the SP PRO with the Grid Fail –
Generator Backup. Step though the wizard to setup the system to suite the appropriate
application.
Note: For more information when stuck through the “Site Configuration Wizard”, right click on
the page and a help guide will appear to help setup the system.
The settings detailed in Appendix I (pages 7 to 8) will be set when the Site Configuration
Wizard is used to configure the SP PRO. Only the settings required to enable Grid Fail –
Generator Backup are shown. The remainder of systems settings will be set by the Site