Roof Down Slope Hole Size

SLOPE

ASHT+

S-2100+

AC

Roof 

Pitch

8"

8"

8"

0 *

14-3/8" (365mm)

16" (406mm)

15" (380mm)

2/12

14-5/8" (371mm)

16-1/4" (413mm)

15-3/8" (390mm)

4/12

15-1/4" (387mm)

16-7/8" (429mm)

16-1/8" (410mm)

6/12

16-1/8" (410mm)

17-7/8" (454mm)

16-7/8" (430mm)

8/12

17-3/8" (441mm)

19-1/4" (489mm)

18-1/4" (465mm)

10/12

18-3/4" (476mm)

20-7/8" (530mm)

19-5/8" (500mm)

12/12

20-3/8" (518mm)

22-5/8" (575mm)

21-3/8" (545mm)

Cross slope hole size

  Put the chimney cap into place.       

  Wash the roof flashing with a solvent or vinegar, then paint it with rust-proof paint.

Table 4               

Figure 22

Figure 23

Figure 31

AC

Air Cooled Chimney

Collar

Chimney

Flashing

Spacer (built 

into flashing)

OFFSET CHIMNEY INSTALLATION

After reaching the location requiring the elbow, proceed as follows. The minimum chimney height 

excluding the fireplace height is shown in 

Table 2.

Notes:

• 

Must return to vertical before penetrating ceiling or floor.

• 

A maximum of 2 offsets are allowed.

After  reaching  the  location  requiring  the 

elbow, proceed as follows:

ASHT+//S2100+/ Chim-

neys

1.  Install  the  first  elbow.    Turn  it  in 

the  required  direction.  Fasten  it  to 

the  chimney  with  the  three  (3)  1/2" 

(12mm) metal screws provided.

2.  Install the necessary lengths to achieve 

the  required  offset.    Lock  the  chimney 

lengths  together:  it  is  recommended  to 

use three (3) 1/2" (12mm) screws.  If the 

offset length is made of two (2) chimney 

lengths use an offset support halfway up 

the offset.  If penetrating a wall, install a 

wall radiation shield (see 

Figure 27

).

3.  Use another elbow to turn the chimney 

vertically. Secure the elbow, using three 

(3) 1/2" (12mm) screws (provided with 

the elbow).

4.  Use a plumb-bob to line up the center of 

the hole. Cut a hole for the chimney in the 

ceiling/floor.  Frame this hole as described 

previously  (see  Chimney  Installation 

Instructions on 

Page 16

).

5.  From  below,  install  a  radiation  shield 

(

Figure 20A

).

6.  A support (ST+ or SO+) must be used on 

the first 15 feet section (5 m).

7.  Continue with the regular installation.

AC chimney

1.  Install the first elbow. Turn it in the required 

direction. To lock it in place, turn 1/8 of 

a turn. Fasten the straps attached to the 

elbow to the surrounding framing using 

nails or drywall screws (

Figure 25

).

2.  Install  the  necessary  chimney  lengths 

to achieve the required offset.  Lock the 

chimney lengths together.  If penetrating 

a wall, use a wall radiation shield (

Figure 

27

).

3.  Use another elbow to turn the chimney 

vertically.  Lock it to the chimney.  Fasten 

the straps attached to the elbow to the 

surrounding framing using nails or drywall 

screws.

4.  Use a plumb-bob to line up the center of 

the hole.  Cut a hole for the chimney in 

the ceiling.  Frame this hole as described 

previously.

5.  From below, install a radiation shield (see 

Figure 20B

).

6.  Continue with the regular installation.

Note:  When  using  AC  chimney,  an  AC8SB 

(H3801) starter section must be used before 

installing an elbow.  When an offset is needed 

immediately off the top of the fireplace, an 

elbow starter section, AC8SB30 (H3802) is 

available.

Содержание HE43-2

Страница 1: ...continuous use as a primary heat source INSTALLATION AND OPERATION INSTRUCTIONS WARNINGS Hot Do not touch The glass and surfaces of this appliance will be hot during operation and will retain heat for...

Страница 2: ...packag ing woodproductswithsynthetic binders i e plywood Plywood lumber and other misc materi alscanproduceabnormallyhigh temperatures sputtering and smoking fires and may contain hazardous chemicals...

Страница 3: ...an energy effi cient heatcirculatingfireplace Youwillreceive a lifetime of comfort and enjoyment from your fireplaceprovideditisinstalled maintainedand operated properly Please read these instructions...

Страница 4: ...period of one year will usually meet that criteria The required drying time will vary depending on the climate Wood that is packed tight together will take longer to dry Seasoned wood is darker in co...

Страница 5: ...r The outside air register supplies oxygen to the fire and allows control of the fire when the doors are closed Thefreshairmustcomefromoutsidethehouse the air intake must not draw air from inside the...

Страница 6: ...framing Creosote formation in a chimney can be minimized by making sure there is always visible flame burning avoid smouldering fires and by proper refuelling techniques Chimney Maintenance Regular c...

Страница 7: ...s of the hinges supports see fastening screws in Figure 5 If a minor angular adjustment is needed you may loosen only two 2 of the three 3 screws using the other as a pivot point How to use the retrac...

Страница 8: ...NTACT OF GLASS CLEANER WITH THE FIREPLACE FACADE CAN PROVOKE PAINT PEELING OFF Gasket Replacement Remove the doors from the unit see Page 7 andlayeachdooronacleanunabrasivesurface To replace the gaske...

Страница 9: ...hout this manual Please give special attentiontotheseinstructionsasyouprogress with your installation Fireplace Installation Procedure 1 Move the fireplace into the desired position follow the recomme...

Страница 10: ...directly on the floor figure 8B Cold Climate Installations Climates where temperatures will fall below 32 F 0 C The heating performance of the appliance will vary depending upon the level of insulatio...

Страница 11: ...loose filling material CovertheinsulationwithDrywallpanels around the fireplace 7 MIN 2 X 3 MIN A G B Rough Framing Face unfinished shown 593mm 23 11 32 K Combustion Air Kit Combustible materials can...

Страница 12: ...using the same insulation as the rest of the building below the attic Finished wall Must have the same fires rating as adjacent ceiling Must be insulated same as adjacent ceiling Local code regulatio...

Страница 13: ...el 3 The outside air register must not be installed more than 10 feet 3 1 m above the base of the fireplace 4 The outside air assembly must draw air from outside the house It must not draw air from th...

Страница 14: ...nnection Connector for Optional Rheostat Thermodisc Automatic Thermal Blower Activator Figure 14 Central Forced Air Kit central forced air kit If this kit is installed this appliance no longer qualifi...

Страница 15: ...f and at least 2 feet 610mm higher than any wall roof or building within 10 feet 3 m of it see Figure 18 If the chimney extends higher than 5 feet 1500mm above its point of contact with the roof it mu...

Страница 16: ...support 5 Then puttheroofflashinginplaceandseal the joint between the roof and the flashing with roofing pitch For sloping roofs place theflashingundertheuppershinglesandon top of the lower shingles...

Страница 17: ...gths use an offset support halfway up the offset If penetrating a wall install a wall radiation shield see Figure 27 3 Use another elbow to turn the chimney vertically Secure the elbow using three 3 1...

Страница 18: ...Lengths Between Elbows 12 18 36 48 12 48 18 48 36 48 48 48 AC 8 15 A 4 13 16 122mm 6 1 8 156mm 11 280mm 14 1 8 359mm 16 7 8 429mm 18 7 16 468mm 23 584mm 26 3 16 665mm B 27 11 16 703mm 33 1 2 851mm 50...

Страница 19: ...gle Hole Size ASHT 8 I D 30 14 3 8 x 36 1 2 365mm x 927mm Canada Only 45 14 3 8 x 24 3 4 556mm x 629mm S 2100 8 I D 30 16 x 40 406mm x 1016mm Canada Only 45 16 x 27 1 4 406mm x 692mm AC 8 I D 30 15 1...

Страница 20: ...ation refer to the instructions provided with the support Universal Offset Support This support is used to support the chimney above an offset When the chimney offset is used to traverse a wall this s...

Страница 21: ...nded at elevations above 4000 feet or in very cold climates where temperatures are likely to fall below 0 F 18 C When using AC chimney an AC8SB H3801 starter section must be used before installing an...

Страница 22: ...to Convert Fireplace for Use with AC Chimney Starter Section adaptor 8 AC AC8SB H3801 Starter 30 Elbow 8 AC AC8SB30 H3802 Outside Air Kit Chimney Required for AC Chimney Installations Chimney Outside...

Страница 23: ...replace with any material 7 feet measured from the base of the fireplace Except the wood framing See Page 11 Figure 9 Chimney 2 50 mm Mantel 48 1219 mm measured from the base of the fireplace Specific...

Страница 24: ...PR COGR2035 31 and 1 each P N PR COGR2035A 16 v Note To order a complete gasket set to seal one glass on a nickel plated door order one each P N PR ISO2748 P N PR ISO2749 and P N PR ISO2750 Contactan...

Страница 25: ...NOTE DIAGRAMS ILLUSTRATIONS ARE NOT TO SCALE 25 Replacement parts HE43 2 PA I N T 18 1 2 3 4 6 7 9 8 10 10 12 11 13 15 16 14 17 19 20 21 22 5...

Страница 26: ...s should be ordered through your Security Chimneys International distributor or dealer Parts will be shipped at prevailing prices at time of order When ordering repair parts always give the following...

Отзывы: