Requirements
There is adequate lab space to accommodate the equipment.
If the mass spectrometer inlet is lower or higher than the range of the CESI 8000
Plus cart, a table or stand of the appropriate height for the CESI 8000 Plus system
is available.
Additional personnel or lifting equipment are available to help the FSE move the
equipment. Four people are recommended.
Electrical Requirements
Electrical Requirements on page 15
N/A
Complete
Requirement
Installation of electrical supplies and fixtures complies with local regulations and
safety standards.
One branch circuit is provided for the CE components. One AC mains supply outlet
is required.
Note:
Do not use extension cords.
The mains supply voltage does not fluctuate more than ± 10% from the nominal
voltage.
The mains supply includes a correctly installed protective earth conductor.
A qualified electrician has determined the appropriate mains supply configuration
based on the system electrical specifications. Refer to
Ventilation and Waste Collection Requirements
Ventilation and Waste Collection Requirements on page 16
N/A
Complete
Requirement
Ventilation of the laboratory environment in which the system will be used
complies with local regulations and the air exchange rate is appropriate for the
work performed.
Waste containers are available as required by local regulations.