Schier | SI-75 Installation Guide
1
Test tank for water tightness
1a
1b
1c
Have a Leak?
Call customer care at 913-951-3300
Hours 8am-5pm CST, M-F
Cap all connection points with 4" cleanout
plugs using pipe thread sealant or tape
approved for use with plastics.
Remove cover. For base unit testing fill with water to
just above the highest connection.
Inspect unit, connections and gaskets for leaks. Check
water level at specific time intervals per local code.
Fill Line
Excavate hole at least 12" larger than interceptor on all sides and 6" deeper than tank bottom. Lay a level bed of
well-packed, crushed aggregate (approximately 3/4" size rock or sand, with no fines) in the base of hole.
12"
12"
6"
6" or more
2
Excavate Burial Pit