PM135 QuickStart 

 

www.satec-global.com 

OPERATION  

The PM135 is operated using the front panel which consists of an LCD display, 12 LEDs and five 
keys as shown below:  

 

Status Line 

Date, time, operation mode, current tariff (T1

T8), phase indicators and power flow direction. 

Operation modes: NORM and TEST. In the TEST mode the energy registers are not 
accumulated and the calibration led is 10 times faster (10 pulses per Wh or varh). 
Phase indication is on when voltage is ok, blinking when below voltage dip set value or marked 
as “-“ when below the interruption set value. 
Power flow direction: Normal flow (generation to load) –  , reverse flow – 

 or no load – 

 

Display Screens 

 
Group (

 to change) 

Screens (

 to go right, 

 to go left). Underlined = included in Auto Scroll 

Voltages 

V L-L  

//  

V L-N  

//

  THD  

//

  Ue  

//

  Hz  

//

  Phase  

//

  Demand 

Currents 

Amps  

//

  THD  

//

  TDD  

//

  K Factor  

//

  Unbalance  

//

  Demand 

Powers 

Total  

//

  L1  

//

  L2  

//

  L3  

//

  Import Demand  

//

  Export Demand 

Demands 

P Import  

//

  P Export  

//

  Amps  

//

  Volts 

Min/Max 

V L-L  

//

  V L-N  

//

  Amps  

//

  I neutral  

//

  P  

//

  PF  

//

  Hz 

Energy 

Import  

//

  Export 

TOU (Import, Export) 

Reg#1  

//

  Reg#2 

Harmonics 

#3  

//

  #5  

//

  #7 … #39 

Spectrum 

V1  

//

  V2  

//

  V3  

//

  I1  

//

  I2  

//

  I3 

Waveform 

L1  

//

  L2  

//

  L3 

Phasor 

 

Digital I/O 

  

Diagnostic 

 

Alarms 

 

Basic Settings 

Page1  

//

  Page2 

Device Info 

Info  

//

  Com 

 

 

 

 

 

 

Diagnostic LED. Off = OK

 

 

Load bar graph 
(full load according to 
CT or in Display Setup) 
 

Title (displayed value, units, 
phase/s) 

Main display  
(real time, min, max) 

Calibration LED  
(1 pulse/Wh or Varh) 

Communication Indication 

Status line (see below) 

Scroll up/down 

Select / Enter 

TAB - Change screen, 
submenu etc. 

Menu / Escape 

Press

 

  

 Press

 

  

 

Press

 

Navigation 

Содержание PM135

Страница 1: ...135 shall be made in accordance with all applicable laws and or regulations and be performed by authorized personnel only MOUNTING Position the PM135 meter in 92 92mm square or 4 round cutout Figure 1 If two PM135 are positioned side by side keep at least 150mm 5 9 between their centers to allow installation of add on modules 140mm 5 5 if only small form modules will be used Attach the PM135 unit ...

Страница 2: ...ernal CT ends with two wires Note 2B 5 1 Pass one wire through the meter CT core 5 2 Connect the wire to one of the meter optional CT wire termination screws 5 3 Connect the second wire from the external CT to the termination screw 6 Connect the measured voltage inputs 7 Connect COM1 RS 485 communication port 8 To connect the optional module 8 1 Make sure that the power is turned off 8 2 Remove th...

Страница 3: ...reens Group to change Screens to go right to go left Underlined included in Auto Scroll Voltages V L L V L N THD Ue Hz Phase Demand Currents Amps THD TDD K Factor Unbalance Demand Powers Total L1 L2 L3 Import Demand Export Demand Demands P Import P Export Amps Volts Min Max V L L V L N Amps I neutral P PF Hz Energy Import Export TOU Import Export Reg 1 Reg 2 Harmonics 3 5 7 39 Spectrum V1 V2 V3 I1...

Страница 4: ...for voltage and current demand 900 Nominal Frequency The nominal frequency 60 Hz Max Demand Load Current 0 CT primary current Other max current 0 Wiring Mode Setup 3 wire 2 element Delta direct connection using 2 CTs 3DIR2 4 wire 3 element Wye direct connection or 3PTs and 3 CTs 4LN3 or 4LL3 3 wire 2 element Open Delta connection using 2 PTs 2 CTs 3OP2 4 wire 2 element Wye connection using 2 PTs 3...