14
English
Ins
tallation Pr
oc
edur
e
Installation Procedure
•
You must keep the cable in a protection tube.
•
Keep distances of 50mm or more between power cable
and communication cable.
•
Maximum length of power cables are decided within
10% of power drop. If it exceeds, you must consider
another power supplying method.
•
The circuit breaker(ELCB or MCCB+ELB) should be
considered more capacity if many indoor units are
connected from one breaker.
•
Use round pressure terminal for connections to the
power terminal block.
•
For wiring, use the designated power cable and
connect it firmly, then secure to prevent out-side
pressure being exerted on the terminal board.
•
Use an appropriate screwdriver for tightening the
terminal screws. A screwdriver with a small head will
strip the head and make proper tightening impossible.
•
Over-tightening the terminal screws may break them.
•
See the table below for tightening torque for the
terminal screws.
Tightening torque
N•m
kgf•cm
M3.5
0.8~1.2
8.0~12.0
M4
1.2~1.8
12.0~18.0
Step 12 Optional: Extending the
power cable
1
Prepare the following tools.
Tools
Spec
Shape
Crimping pliers
MH-14
Connection sleeve
(mm)
20xØ6.5 (HxOD)
Insulation tape
Width 19 mm
Contraction tube
(mm)
70xØ8.0 (LxOD)
2
As shown in the figure, peel off the shields from the
rubber and wire of the power cable.
•
Peel off 20 mm of cable shields from the pre-
installed tube.
CAUTION
•
For information about the power cable
specifications for indoor and outdoor units, refer
to the installation manual.
•
After peeling off cable wires from the pre-
installed tube, insert a contraction tube.
20
20
20
20
60
120
180
Power cable
Pre-installed tube for the power cable
(Unit: mm)
DVM Boracay_IM_EN_DB68-06417A-00_16.09.22.indd 14
2016/9/22 11:29:14