COMMISSIONING
5.1 Start Up and Shut Down the Micro-Inverter
5.1.1 Start Up
Step 1: While installation is all finished, turn on the main utility-grid AC circuit breaker.
Step 2: Wait for two minutes and your system will start running.
5.1.2 Shut Down
Step1: Disconnect the micro-inverter and PV modules.
Step 2: The LED indicator will light off and the system will shut down.
5.1.3 Introduction of the LED Indicator
The LED will flash green and red at start up. The definition of LED is shown as below.
Status
Indicates
Green
Solid
Working normally
Green
Breathing
Standby/Waiting
Red
Flashing 1
Unable to connect
Red
Solid
Fault
Red
Breathing
Upgrading
Red & Green
Off
Not working
Note: 1. The breathing cycle is 6s;
2. Flashing 1 is one cycle lighting up for 1s and off for 1s.
3. Flashing 2 is one cycle lighting up for 1s and off for 3s
5.2 eSAJ APP Connection
5.2.1 Downloading the eSAJ Home App
1. The
eSAJ Home
App can be sued for both nearby and remote monitoring. It supports Bluetooth, 4G and
Wi-Fi module to communicate with the device.
2. On your mobile phone, search f
or “
eSAJ Home
” in the App store and download th
e App.
5
.