355 JUST FOR KIDS
Assembly Instructions
Page 17 of 25
3. On the top surface of each Just for Kids Base, there are two (2)
holes that reveal the anchor holes (Fig. 9).
SAFETY GLASSES, TO BE WORN DURING DRILLING,
ANCHOR INSTALLATION AND SETTING!
4. Drill the 4 holes for the floor anchors using the anchor holes in the 2 Just for Kids Bases as
guides (see Fig. 8 above). Drill the holes 5/8” diameter to a depth equal to the length (2 inches) of
the floor 1/8”.
REFER TO PAGE 9 FOR COMPLETE INSTRUCTIONS ON PROPER INSTALLATION OF
FLOOR ANCHORS!
NEVER PLACE A FLOOR ANCHOR INTO A SEAM/CRACK, OR AN AREA WITHIN 9”
FROM A SEAM/CRACK OR OUTSIDE EDGE OF THE CONCRETE FLOOR.
5. Move the apparatus aside. Vacuum the holes to remove all dust and concrete chips.
6. Insert the floor anchors, threaded end up & slotted end down, into the drilled holes. Ensure the
top of the floor anchor is flush with or just below the top of the concrete.
7. Set each of the floor anchors by striking the plunger in the center of the floor anchor as per page
9.
ENSURE THAT THE ANCHORS ARE PROPERLY SET OR THE SAFE USE OF THE
EQUIPMENT MAY BE COMPROMISED!
8. Reposition the apparatus over the floor anchor and bolt down the Just for Kids Bases (see Fig. 8)
loosely. Ensure that Bases are parallel to each other and install 1 or 2 Just for Kids Upright
(#355-05) on each pair of Bases (#355-01). This will assist in maintaining the correct width
between the bases as well as maintaining them parallel to each other.
9. Now that the uprights are installed, tighten the bolts down on the bases securely.
10. Install the plastic caps in the indicated holes shown in Fig. 5 of the top of the Bases.
Fig. 9