Surface temperature
– When operating independently of the ambient air with nominal output, the design does not allow temperatures > 70 °C on
any component outside the unit panels. Therefore, no minimum distance is required to components made with flammable
materials.
– A minimum distance of 20 mm between the flue gas pipe and flammable components should be maintained with partial
ambient air-independent and ambient-dependent operation.
– Do not store or use highly combustible and flammable materials in the immediate vicinity of the oil condensing boiler.
3.3
Initial start-up
After the oil condensing boiler has been installed and fully connected, it can be started up by trained staff.
3.4
Instruction and handover to the user
The oil condensing burner will be handed over to you after it has been started up by the technicians. During handover, the installer
will train you on how to operate and use the oil condensing boiler.
The training will consist of at least the following:
– Explanation of the safe and intended use of the oil condensing boiler and the legal responsibilities which you have as the
operator of the oil heating system.
– Explanation of the operating elements and the setting facilities that you can use.
– Explanation of the operating modes and instructions for economical and energy-saving operation.
– Explanation of the required cleaning and maintenance work which you can carry out.
– Procedure in the event of a fault.
A flue gas temperature sensor integrated in the control unit of the oil condensing boiler triggers a safety
shutdown if the flue gas temperature is too high.
No additional insulation is needed on site in Germany.
WARNING!
An oil condensing boiler not started up properly can be a health and safety risk endangering human life and
adversely affect its operation.
• Start-up of the oil condensing boiler may only be carried out by authorised and trained heating engineers.
The requirements and tests before start-up, the start-up activities and the required tests are described in detail
in the installation and maintenance instructions for the expert operation mode.
The scope of supply includes an installation and training form. Correct handover should be recorded in the files