Install the Chargepoint
Zura Intelligent EV Charging Unit
EVZM-01-V01R1 Installation and Operation Manual
Page
25
of
42
December 2022
Install the Chargepoint
IMPORTANT:
All electrical work must be performed in accordance with the current
legislation applicable in the geographical region of the installation.
CAUTION: Equipment Damage – Sensitive Equipment
If you will be performing insulation resistance tests on the power supply cables, it is
advised to be done BEFORE connecting the power cable to the chargepoint. The high
voltages applied during the test may damage sensitive components if tested after the
cable is connected.
CAUTION: Equipment Damage
Do NOT use power tools to remove/install panel fixings.
Power tools can damage the fixings, making the panel difficult to remove.
Use hand tools ONLY and do not overtighten fasteners.
IMPORTANT:
If
Load Balancing
is required, install it before completing the standard
installation. Refer to
page 29 Install Load Balancing
shown immediately after these
‘standard’ installation instructions.
Alternatively, if a third-party Load Balancing or Load Management device/system is to
be used, refer to the manufacturer’s instructions.
CAUTION: Equipment Damage
Make sure to support the front section of the chargepoint. Do not strain cable
connections or the cables that run between the front and rear halves of the enclosure.
1. Locate the Front Fascia Clip on the
bottom of the chargepoint. The
outer fascia is held in place by the
clip at the bottom edge, locating
spigots around the mid position and
a hook assembly at the top.
Figure 25 Front Fascia Clip