CHECKING EQUIPMENT BEFORE YOU INSTALL 

Inspect the unit completely upon receipt from the freight carrier before signing the bill of lading. Inspect the appliance 
and all accompanying parts for signs of impact or mishandling. Verify the total number of pieces shown on packing 
slips with those actually received. Contact the freight carrier immediately if any damage or shortage is detected. 
 

WARRANTY 

Factory warranty does not cover improper installation or operation.  (See warranty for complete details).  
Warranty exclusions include but are not limited to failure or malfunctions resulting from: 
 

1.  Failures to properly apply, install, operate, or maintain the appliance in accordance to printed instructions. 
2.  Abuse, alteration, accident, fire, flood and the like. 
3.  Sediment or lime buildup, freezing or any other conditions causing inadequate circulation.  
4.  Corrosive or contaminated atmosphere. 

 

CODES

 

The equipment shall be installed in accordance with those installation regulations in force in the local area where the 
installation is to be made. These shall be carefully followed in all cases. Authorities having jurisdiction shall be 
consulted before installation is made. In the absence of such requirements, the installation shall conform to the latest 
edition of the National Fuel Gas Code, ANSI Z223.1 and with the National Electrical Code, NFPA 70. Where required 
by the authority having jurisdiction, the installation must conform to American Society of Mechanical Engineers Safety 
Code for Controls and Safety Devices for Automatically Fired Boilers, No. (CSD-1). All appliances conform to the 
latest edition of the ASME Boiler and Pressure Vessel Code, Section IV. Where required by the authority having 
jurisdiction, the installation must comply with the Canadian Association Code, CAN/CSA-B149.1 and/or B149.2 and/or 
local codes.  
 

LOCATION 

 

1.  Locate the unit in a clean and dry area as close as possible to the greatest hot water usage and as near to 

gas,   oil, steam, boiler water and/or electrical power as practical. 

2.  Install the unit on a firm, level foundation. 
3.  Locate the foundation on a pitched floor near a suitable drain, or make other provisions to prevent contact to 

areas of the building subject to water damage should the boiler or a water connection leak. The drain must be 
sufficient to contain water in excess of 210°F. 

 

INSTALLATION 
 
WARNING:  Use industry standard safe rigging methods when attempting to lift or move this product. Failure 
to follow these instructions could result in property damage, serious injury or death. One common method 
includes the use of straps and spreader bars, lifting from the water heater base skid assembly. 

 

 

1.  Check the data decal on the boiler. Be sure the electrical, water, oil, or gas supply is adequate for the 

installation. 

2.  Carefully remove all shipping supports and bracing. (Float type devices have shipping plugs blocking the 

float). 

3.  Install shut-off valves and unions on the inlet and outlet water piping for servicing. Use caution when 

threading pipe nipples into tank connections to prevent cross threading, or over-tightening. Always use a 
back-up wrench on tank nipples when tightening unions, valves, etc. 

4.  Insulate hot water and return circulation lines. Insulate cold water supply lines if subject to freezing during 

shutdown periods. 

IMPORTANT: Do not use the plumbing connected to the appliance as a ground for 

welding or any other purpose. 

5. 

The boiler is equipped with a temperature and pressure relief valve(s) rated for the input. Pipe the relief valve 
discharge to a suitable open drain. The drain pipe may not be smaller than the relief valve opening and must 
be secured to prevent it from lifting out of the drain under discharge pressure. Do not install valves or 
restrictions in the discharge line. 

 

6.  Pipe the drain valve to a suitable open drain. 

Содержание EPV SERIES

Страница 1: ...on adjustment alteration service or maintenance can cause property damage personal injury exposure to hazardous materials or loss of life Refer to the information contained in this manual A qualified...

Страница 2: ...oose fitting clothing eye protection and gloves FIRST AID MEASURES If any of the irritations listed persists seek medical attention Eyes Flush with water Skin Wash with soap and warm water Ingestion D...

Страница 3: ...THE PHYSICALLY HANDICAPPED HOSPITALS AND NURSING HOMES ELDER CARE FACILITIES AND REST HOMES ORPHANAGES AND CHILD CARE FACILITIES OTHER INSTALLATIONS WHERE RESPONSE TO CONTACT WITH HOT WATER MAY BE SLO...

Страница 4: ...ng control 5 I beam skid 17 Drip leg 6 Flue outlet 18 Electronic LWCO control 7 Gas inlet 19 Temperature pressure gauges 8 Induced draft blower motor 20 Alarm bell 9 Circulating pump 21 Differential a...

Страница 5: ...e CAN CSA B149 1 and or B149 2 and or local codes LOCATION 1 Locate the unit in a clean and dry area as close as possible to the greatest hot water usage and as near to gas oil steam boiler water and...

Страница 6: ...ed to the correct points 3 When remote on off or lead lag enable operation is used remove jumper from R1 and R2 and wire in series 4 A proper earth ground for this unit must be provided A single condu...

Страница 7: ...ision shall be made to drain off and dispose of condensate from a venting system A fitting no more than 18 from the combustion blower should be provided in the venting to route vent condensate away fr...

Страница 8: ...use the correct terminations could result in carbon monoxide poisoning causing personal injury or loss of life Air inlet duct is defined as a means of ducting the outside combustion air to the burner...

Страница 9: ...EPV SERIES CONDENSING WATER BOILER 34 501 07 13 9 Typical Termination Locations for Vertical Vent Pipes Termination of less than 10 feet Figure 501 2 Termination of more than 10 feet Figure 501 3...

Страница 10: ...eparation to prevent recirculation of combustion products Although the National Fuel Gas Code provides minimum clearances use sound engineering judgment considering prevailing winds obstructions and t...

Страница 11: ...ction Figure 501 6 1 Static fan 11 Manual shutoff valves 2 End cap 12 Main gas pressure regulator 3 Gas nozzle assembly 13 Main gas valve 4 Pressure plate 14 Pilot gas valve 5 Blast tube burner housin...

Страница 12: ...wo stage models a second operating thermostat is used to control the second stage operation and should be set approximately 10 F below the primary operator Adjustment may be made by turning the thermo...

Страница 13: ...at least thirty seconds 17 When the blower motor starts the air damper will open and the airflow proving light on the MEC120 should be on This indicates a positive airflow condition If the air proving...

Страница 14: ...fold gas pressure slightly and take readings until CO is within proper range Optimum reading is no CO 24 If manifold pressure was changed during startup take a final CO and O2 reading 25 Record CO2 an...

Страница 15: ...07 13 15 Record the following information for future use 1 Manifold gas pressure W C 2 Vent pressure W C 3 O2 reading 5 7 4 CO2 reading 8 9 5 CO reading ppm less than 300 ppm 6 NOx reading ppm 7 Vent...

Страница 16: ...R ANY REASON CONSULT THE FACTORY FOR INSTRUCTIONS 3 Examine the venting system at least monthly for proper connections alignment or the presence of corrosion If corrosion appears the boiler must not b...

Страница 17: ...est to insure proper operation prior to returning the boiler to service Remove the pipe plugs from the tees and crosses and make certain the cross connecting piping is clean and free of obstructions C...

Страница 18: ...he holes in the pressure plate 16 Inspect electrodes for cracked ceramic or loose retaining studs that hold the wire within the ceramic Select the proper pressure plate hole to place each electrode an...

Страница 19: ...N REPORT DATE BURNER INSPECTION COMBUSTION ANALYSIS TANK INSPECTION TANK FLUSH CLEANOUT TANK FITTING INSPECTION VENT INSPECTION THERMOST AT INPSECTION GAS TRAIN LEAK TEST Recommended Inspection Interv...

Страница 20: ...17 i Defective circulation pump Repair or replace j Regulator vent line s plugged Remove blockage 2 OCCASIONAL LOCKOUTS FOR NO APPARENT REASON a Gas pilot ignition failure Check to see that ignition i...

Страница 21: ...OTOR RUNS AND PILOT LIGHTS BUT THE MAIN GAS FLAME IS NOT ESTABLISHED a Main shutoff or test cock closed Check to make certain fully open b Pilot flame signal reading too low to pull in flame safeguard...

Страница 22: ...nsate for small line Do not raise pressure so high that under static no flow conditions the pressure exceeds the maximum allowable pressure to the gas train components on the burner f Automatic gas va...