Start-up, calibration and operation of the burner
Only for RS 44/E MZ three-phase
As the burner is not fitted with a device to check the sequence of
the phases, the motor rotation may be incorrect.
As soon as the burner starts up, go in front of the cooling fan of
the fan motor and check it is rotating anticlockwise. See Fig. 32.
If this is not the case:
–
place the switch of Fig. 32 in position
“0”
and wait for the
control box to carry out the switch-off phase;
–
disconnect the burner from the electrical supply;
–
Invert the phases on the three-phase power supply of the in-
verter (see the specific inverter manual).
Follow the
6.4
Burner adjustment
6.4.1
Firing output
According to the regulation EN 676.
Burners with MAX output up to 120 kW
Ignition can be performed at the maximum operation output level.
Example:
–
max. operation output:
120 kW
–
max. firing output:
120 kW
Burners with MAX output above 120 kW
Ignition must be performed at a lower output than the max. oper-
ation output.
If ignition output does not exceed 120 kW, no calculations are re-
quired. If ignition output exceeds 120 kW, the regulations pre-
scribe that the value be defined according to the control box
safety time "ts":
for ts = 3 s, ignition output must be equal to, or lower than, 1/3 of
max. operation output.
Example:
MAX operation output of 450 kW.
The ignition output must be equal to, or less than, 150 kW with
ts = 3 s
In order to measure the ignition output:
disconnect the plug-socket 6)(Fig. 5 at page 13) on the ioni-
sation probe cable (the burner will fire and then go into lock-
out after the safety time has elapsed);
perform 10 ignitions with consecutive lockouts;
on the meter, read the quantity of gas burned:
this quantity must be equal to, or lower than, the quantity
given by the formula, for ts = 3 s:
Vg
volume supplied in ignitions carried out (Sm
3
)
Qa
ignition delivery (Sm
3
/h)
n
number of ignitions (10)
ts
safety time (sec)
Example for gas G 20 (9.45 kWh/Sm
3
):
ignition output 150 kW corresponding to 15.87 Sm
3
/h.
After 10 ignitions with lockout, the delivery indicated on the meter
must be equal to, or less than:
6.4.2
Maximum output
The MAX output must be set within the firing rate (Fig. 2 at
page 10).
Gas adjustment
Measure the gas delivery on the meter.
As a general rule, this value can be found on Tab. K at page 27,
just read the gas pressure on the pressure gauge (Fig. 39 at
page 51) and follow the indications given on page 27.
–
If it is necessary to reduce it, lower the output gas pressure
via the pressure adjuster located beneath the gas valve.
–
If it needs to be increased, increase the output gas pres-
sure via the adjuster.
Air adjustment
If necessary vary the degrees of the air servomotor.
6.4.3
Minimum output
The MIN output must be set within the firing rate (Fig. 2 at
page 10).
DANGER
This operation must be carried out with the electri-
cal supply disconnected.
Fig. 32
20064705
Vg =
3600
Qa
(max. burner delivery)
x n x ts
Vg =
3600
15.87 x 10 x 3
= 0.132 Sm
3
Содержание RS 34/E MZ
Страница 2: ...Translation of the original instructions ...
Страница 65: ...63 20068131 GB Appendix Electrical panel layout RS 34 E MZ ...
Страница 66: ...20068131 64 GB Appendix Electrical panel layout RS 44 E MZ ...
Страница 67: ...65 20068131 GB Appendix Electrical panel layout RS 44 E MZ 3Ph ...
Страница 68: ...20068131 66 GB Appendix Electrical panel layout RS 34 44 E MZ ...
Страница 69: ...67 20068131 GB Appendix Electrical panel layout RS 44 E MZ 3Ph ...
Страница 70: ...20068131 68 GB Appendix Electrical panel layout ...
Страница 71: ...69 20068131 GB Appendix Electrical panel layout ...
Страница 72: ...20068131 70 GB Appendix Electrical panel layout ...
Страница 73: ...71 20068131 GB Appendix Electrical panel layout ...
Страница 75: ......